7424-7426 N LEMP AVE 91605
Certificate Information: 7424-7426 N LEMP AVE 91605
- Application / Permit
- 25016-20000-30087
- Plan Check / Job No.
- B25VN29682
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan Convert existing portion(409SF) of residence to an ADU per LAMC 12.22 A.33 (c) and (e).
- Permit Issued
- Issued on 11/25/2025
- Issuing Office
- Current Status
- Issued on 11/25/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/10/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/15/2025 | SAMUEL GONZALEZ |
| Corrections Issued | 10/15/2025 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 11/12/2025 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 11/14/2025 | SAMUEL GONZALEZ |
| Plan Check Approved | 11/22/2025 | SAMUEL GONZALEZ |
| Issued | 11/25/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/24/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 10/24/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 10/27/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Cr Builders Llc; Lic. No.: 1131278-B | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/11/2025 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 12/12/2025 | Corrections Issued | JOSE AVILA |
| BUILDING-Rough-Frame | 12/26/2025 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 12/26/2025 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 12/26/2025 | Conditional Approval | JOSE AVILA |
| HVAC-Rough | 12/26/2025 | Approved | JOSE AVILA |
| PLUMBING-Rough | 12/26/2025 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2025 | Partial Approval | JOSE AVILA |
| ELECTRICAL-Rough | 1/27/2026 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 1/27/2026 | Approved | JOSE AVILA |
| HVAC-Rough | 1/27/2026 | Approved | JOSE AVILA |
| PLUMBING-Rough | 1/27/2026 | Approved | JOSE AVILA |
| Wood Frame | 1/27/2026 | Not Ready for Inspection | JOSE AVILA |
| Interior/Exterior Lathing | 3/3/2026 | Partial Approval | GAREN HAYRAPETYAN |
| Wood Frame | 3/3/2026 | Corrections Issued | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 3/5/2026 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 3/5/2026 | Approved | GAREN HAYRAPETYAN |
| Insulation | 3/9/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Insulation | 3/17/2026 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Insulation | 3/31/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 3/31/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 4/6/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 4/6/2026 | Approved | ROBERTO PALACIOS-LOPEZ |