7698 N LOUISE AVE 91406
Certificate Information: 7698 N LOUISE AVE 91406
- Application / Permit
- 25016-20000-29568
- Plan Check / Job No.
- B25VN29125
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Convert existing detached garage and workroom to A.D.U. per LAMC 12.22 A.33 (b)(1). Design per WFPP.
- Permit Issued
- Issued on 12/3/2025
- Issuing Office
- Current Status
- Issued on 12/3/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/8/2025 | CAROLEAN BASMA |
| Corrections Issued | 10/9/2025 | CAROLEAN BASMA |
| Applicant returned to address corrections | 10/20/2025 | CAROLEAN BASMA |
| Applicant returned to address corrections | 10/22/2025 | AMY GUEVARRA |
| Plan Check Approved | 11/20/2025 | AMY GUEVARRA |
| Issued | 12/3/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/17/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 10/17/2025 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 10/20/2025 | MICHAEL BROWN |
| Construction near power lines | Cleared | 11/19/2025 | GEVORK KARAPETYAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/9/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Pre-Inspection | 12/9/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Pre-Inspection | 12/15/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Pre-Inspection | 12/16/2025 | No Access for Inspection | GAREN HAYRAPETYAN |
| Pre-Inspection | 1/5/2026 | Corrections Issued | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 1/12/2026 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 4/2/2026 | Not Ready for Inspection | KEVIN BERBERYAN |
| HVAC-Rough | 4/2/2026 | Corrections Issued | KEVIN BERBERYAN |
| Insulation | 4/2/2026 | Approved | KEVIN BERBERYAN |
| Sewer | 4/2/2026 | Approved | KEVIN BERBERYAN |
| Smoke Detectors | 4/2/2026 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 4/17/2026 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 4/17/2026 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Rough | 4/17/2026 | Approved | KIRK SANDERS |
| Sewer | 4/17/2026 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 4/27/2026 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 4/27/2026 | Approved | VINCENT HANLEY |
| Green Building Rough | 4/27/2026 | Approved | VINCENT HANLEY |
| Insulation | 4/27/2026 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 4/27/2026 | Approved | VINCENT HANLEY |
| Drywall Nailing | 5/6/2026 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 5/6/2026 | Not Ready for Inspection | KIRK SANDERS |
| Final | 6/2/2026 | Corrections Issued | MICHAEL CORTEZ |
| Green Building Final | 6/2/2026 | Corrections Issued | MICHAEL CORTEZ |
| SGSOV-Seismic Gas S/O Valve | 6/2/2026 | SGSOV Not Required | MICHAEL CORTEZ |