7714-7716 N ATOLL AVE 91605

Certificate Information: 7714-7716 N ATOLL AVE 91605

Application / Permit
25016-20000-29313
Plan Check / Job No.
B25VN28817
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 10/21/2025
Issuing Office
Current Status
CofO Issued on 6/8/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/30/2025 APPLICANT
Assigned to Plan Check Engineer 10/6/2025 JEROME MAGAT PALMA
Corrections Issued 10/7/2025 JEROME MAGAT PALMA
Building Plans Picked Up 10/14/2025 APPLICANT
Plan Check Approved 10/21/2025 YAQUB MIRZA
Issued 10/21/2025 APPLICANT
CofO in Progress 5/19/2026 OGANES TARAKHCHYAN
Permit Finaled 6/8/2026 RUBEN SALAS
CofO Issued 6/8/2026 RUBEN SALAS
Permit Finaled 6/8/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/9/2025 MICHAEL BROWN
Sewer availability Cleared 10/9/2025 MICHAEL BROWN
Eng Process Fee Ord 176,300 Cleared 10/14/2025 SAFA JAVANMARDI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/12/2025 Partial Approval OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 12/16/2025 Approved OGANES TARAKHCHYAN
Footing/Foundation/Slab 12/16/2025 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 12/16/2025 Partial Approval OGANES TARAKHCHYAN
Sewer 12/16/2025 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 2/6/2026 Not Ready for Inspection OGANES TARAKHCHYAN
HVAC-Rough 2/6/2026 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 2/6/2026 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 2/10/2026 Approved OGANES TARAKHCHYAN
HVAC-Rough 2/10/2026 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 2/10/2026 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 2/17/2026 Partial Approval OGANES TARAKHCHYAN
Green Building Rough 2/17/2026 Not Ready for Inspection OGANES TARAKHCHYAN
Interior/Exterior Lathing 2/17/2026 Corrections Issued OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 2/26/2026 Approved OGANES TARAKHCHYAN
Insulation 2/26/2026 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 2/26/2026 Partial Approval OGANES TARAKHCHYAN
Drywall Nailing 3/6/2026 Approved DAVID MATSON
Shower Pan 3/6/2026 Approved DAVID MATSON
Interior/Exterior Lathing 3/11/2026 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 4/30/2026 No Access for Inspection OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 4/30/2026 SGSOV Not Ready OGANES TARAKHCHYAN
BUILDING-Rough-Frame 5/7/2026 Approved OGANES TARAKHCHYAN
Final 5/7/2026 No Access for Inspection OGANES TARAKHCHYAN
Green Building Final 5/7/2026 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Rough 5/7/2026 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 5/7/2026 SGSOV Not Ready OGANES TARAKHCHYAN
ELECTRICAL-Final 5/13/2026 Approved OGANES TARAKHCHYAN
HVAC-Final 5/13/2026 Approved OGANES TARAKHCHYAN
PLUMBING-Final 5/13/2026 Approved OGANES TARAKHCHYAN
Final 5/18/2026 OK to Issue CofO OGANES TARAKHCHYAN
Green Building Final 5/18/2026 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 5/18/2026 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 5/18/2026 Approved OGANES TARAKHCHYAN
Verify Rec and Parks Fee Memo 5/18/2026 Approved OGANES TARAKHCHYAN