4215 N KRAFT AVE 91604

Certificate Information: 4215 N KRAFT AVE 91604

Application / Permit
25016-20000-29123
Plan Check / Job No.
B25VN28567
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 66323(a)(1).
Permit Issued
Issued on 12/3/2025
Issuing Office
Current Status
Issued on 12/3/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/29/2025 APPLICANT
Assigned to Plan Check Engineer 10/1/2025 GIOVANNY CHAVEZ
Corrections Issued 10/2/2025 GIOVANNY CHAVEZ
Applicant returned to address corrections 10/22/2025 GIOVANNY CHAVEZ
Applicant returned to address corrections 10/24/2025 PINANK PATEL
Applicant returned to address corrections 10/28/2025 GIOVANNY CHAVEZ
Plan Check Approved 10/30/2025 GIOVANNY CHAVEZ
Issued 12/3/2025 APPLICANT

Permit Application Clearance Information

ZI Cleared 10/3/2025 MAYELA VILLA
Address approval Cleared 10/17/2025 MICHAEL BROWN
Sewer availability Cleared 10/17/2025 MICHAEL BROWN
Eng Process Fee Ord 176,300 Cleared 10/20/2025 MICHAEL BROWN

Contact Information

Contractor 1 Degree Construction Inc; Lic. No.: 1075129-B       ,
Contractor 1 Degree Construction; Lic. No.: 1075129-B       ,
Engineer Erdelyi,, Peter Tibor; Lic. No.: C26962       ,

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/9/2025 Corrections Issued CRAIG DAVIS
Underground Mechanical 12/9/2025 Corrections Issued CRAIG DAVIS
Footing/Foundation/Slab 12/12/2025 Approved JAVIER RAMOS JR
PLUMBING-Rough 12/12/2025 Partial Approval JAVIER RAMOS JR
Deputy Drilled-In Anchors 12/15/2025 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 12/15/2025 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 1/5/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 1/5/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 1/20/2026 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 1/20/2026 Approved JAVIER RAMOS JR
Green Building Rough 1/20/2026 Approved JAVIER RAMOS JR
HVAC-Rough 1/20/2026 Corrections Issued JAVIER RAMOS JR
Underground Mechanical 1/20/2026 Partial Approval JAVIER RAMOS JR
Wood Frame 1/20/2026 Corrections Issued JAVIER RAMOS JR
HVAC-Rough 2/11/2026 Partial Approval JAVIER RAMOS JR
Interior/Exterior Lathing 2/11/2026 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 2/11/2026 Partial Approval JAVIER RAMOS JR
Sewer 2/11/2026 Partial Approval JAVIER RAMOS JR
Underground Mechanical 2/11/2026 Partial Approval JAVIER RAMOS JR
Wood Frame 2/11/2026 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 4/6/2026 Partial Inspection JAVIER RAMOS JR
ELECTRICAL-Rough 4/6/2026 Approved JAVIER RAMOS JR
HVAC-Rough 4/6/2026 Not Ready for Inspection JAVIER RAMOS JR
PLUMBING-Rough 4/6/2026 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 4/14/2026 Approved JAVIER RAMOS JR
Insulation 4/14/2026 Approved JAVIER RAMOS JR
Drywall Nailing 4/27/2026 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 4/27/2026 Approved JAVIER RAMOS JR
Shower Pan 4/27/2026 Approved JAVIER RAMOS JR