7345 W VALMONT ST 91042
Certificate Information: 7345 W VALMONT ST 91042
- Application / Permit
- 25016-20000-28786
- Plan Check / Job No.
- B25VN28190
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) UNPERMITTED STRUCTURE BUILT BEFORE JANUARY 1, 2020 TO (N) ACCESSORY DWELLING UNIT PER GCS 66332.
- Permit Issued
- Issued on 1/15/2026
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/29/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/25/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/30/2025 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 10/2/2025 | SEWADA ZADOORIAN MILAGARDI |
| Building Plans Picked Up | 10/3/2025 | APPLICANT |
| Plan Check Approved | 12/30/2025 | ISIS ARGUETA |
| Issued | 1/15/2026 | APPLICANT |
| CofO in Progress | 4/10/2026 | NICHOLAS TROWBRIDGE |
| Permit Finaled | 4/29/2026 | RUBEN SALAS |
| CofO Issued | 4/29/2026 | RUBEN SALAS |
| Permit Finaled | 4/29/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/12/2025 | ROSE STEIN-WENDT |
| Construction near power lines | Cleared | 11/12/2025 | WALTER RAMIREZ |
| Construction within easement | Cleared | 11/12/2025 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/12/2025 | ROSE STEIN-WENDT |
| Grading Pre-Inspection | Cleared | 11/12/2025 | CHARLES POWELL |
| Sewer availability | Cleared | 11/12/2025 | ROSE STEIN-WENDT |
| Specific Plan | Cleared | 12/4/2025 | ERICK MARCHENA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 1/23/2026 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Pre-Inspection | 2/4/2026 | Partial Inspection | NICHOLAS TROWBRIDGE |
| Pre-Inspection | 2/18/2026 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Pre-Inspection | 3/24/2026 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 4/8/2026 | Approved | NICHOLAS TROWBRIDGE |
| Final | 4/8/2026 | OK to Issue CofO | NICHOLAS TROWBRIDGE |
| Green Building Final | 4/8/2026 | Approved | NICHOLAS TROWBRIDGE |
| Green Building Rough | 4/8/2026 | Approved | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 4/8/2026 | SGSOV Approved | NICHOLAS TROWBRIDGE |
| Smoke Detectors | 4/8/2026 | Approved | NICHOLAS TROWBRIDGE |