1075-1075 1/2 E MARCO PL 90291

Certificate Information: 1075-1075 1/2 E MARCO PL 90291

Application / Permit
25016-20000-28666
Plan Check / Job No.
B25VN28041
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT PORTION OF ATTACHED GARAGE TO ADU PER GC 66323(a)(1) AND CONVERT PORTION OF GARAGE TO LAUNDRY FOR SFD.
Permit Issued
Issued on 11/12/2025
Issuing Office
Current Status
Issued on 11/12/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/24/2025 APPLICANT
Assigned to Plan Check Engineer 9/30/2025 SERGIO MUNIZ
Corrections Issued 10/1/2025 SERGIO MUNIZ
Building Plans Picked Up 10/9/2025 APPLICANT
Plan Check Approved 11/3/2025 SERGIO MUNIZ
Issued 11/12/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/28/2025 DERRICK MAGEE
Eng Process Fee Ord 176,300 Cleared 10/28/2025 DERRICK MAGEE
Sewer availability Cleared 10/28/2025 DERRICK MAGEE
Specific Plan Cleared 10/30/2025 RICHARD WOO

Contact Information

Contractor So Cal Kitchen Bath Inc; Lic. No.: 1026689-B 14007 PALAWAN WAY UNIT 316      MARINA DEL REY, CA 90292
Engineer Manoukian,, Krikor Kerop; Lic. No.: C87010 2310 W MAGNOLIA BLVD STE A      BURBANK, CA 91506

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/17/2025 Conditional Approval JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 11/20/2025 Corrections Issued RUBEN RIVAS
Footing/Foundation/Slab 11/20/2025 Corrections Issued RUBEN RIVAS
Footing/Foundation/Slab 12/1/2025 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 12/1/2025 Partial Approval ANTHONY EGSON
Deputy Drilled-In Anchors 12/18/2025 Partial Approval RUBEN RIVAS
Footing/Foundation/Slab 1/5/2026 Approved RUBEN RIVAS
Rough-Elec/Plmb/HVAC 1/22/2026 Corrections Issued RUBEN RIVAS
Rough-Elec/Plmb/HVAC 1/28/2026 Corrections Issued RUBEN RIVAS
Shower Pan 1/28/2026 Approved RUBEN RIVAS
HVAC-Rough 3/10/2026 Not Ready for Inspection RUBEN RIVAS
ELECTRICAL-Rough 3/23/2026 Corrections Issued RUBEN RIVAS
HVAC-Rough 3/23/2026 Corrections Issued RUBEN RIVAS
ELECTRICAL-Rough 3/26/2026 Corrections Issued RUBEN RIVAS
HVAC-Rough 3/26/2026 Corrections Issued RUBEN RIVAS
ELECTRICAL-Rough 4/1/2026 Approved RUBEN RIVAS
HVAC-Rough 4/1/2026 Approved RUBEN RIVAS
BUILDING-Rough-Frame 4/2/2026 Approved RUBEN RIVAS
Green Building Rough 4/2/2026 Approved RUBEN RIVAS
BUILDING-Rough-Frame 4/8/2026 Approved RUBEN RIVAS
Insulation 4/8/2026 Approved RUBEN RIVAS
Drywall Nailing 4/15/2026 Approved RUBEN RIVAS
Interior/Exterior Lathing 4/15/2026 Corrections Issued RUBEN RIVAS