8535-8537 N PENFIELD AVE 91306

Certificate Information: 8535-8537 N PENFIELD AVE 91306

Application / Permit
25016-20000-28621
Plan Check / Job No.
B25VN27989
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 66323(a)(1). CONSTRUCTION DESIGN PER ENGR
Permit Issued
Issued on 10/14/2025
Issuing Office
Valley
Current Status
CofO Issued on 4/21/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/23/2025 APPLICANT
Assigned to Plan Check Engineer 9/29/2025 ARTIN ZARUKIAN
Corrections Issued 9/30/2025 ARTIN ZARUKIAN
Building Plans Picked Up 10/1/2025 APPLICANT
Plan Check Approved 10/2/2025 HAYATO TSUCHIYA
Issued 10/14/2025 APPLICANT
CofO in Progress 4/16/2026 CHRIS CHRISTENSEN
Permit Finaled 4/21/2026 JOHN JANSON
CofO Issued 4/21/2026 JOHN JANSON
Permit Finaled 4/21/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 10/1/2025 MICHAEL BROWN
Eng Process Fee Ord 176,300 Cleared 10/1/2025 MICHAEL BROWN
Sewer availability Cleared 10/1/2025 MICHAEL BROWN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/16/2025 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 11/3/2025 Partial Approval CHRIS CHRISTENSEN
Sewer 11/3/2025 Approved CHRIS CHRISTENSEN
Pre-Inspection 11/21/2025 Approved CHRIS CHRISTENSEN
Underground Mechanical 11/25/2025 Not Ready for Inspection CHRIS CHRISTENSEN
BUILDING-Rough-Frame 12/1/2025 Partial Approval CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 12/1/2025 Approved CHRIS CHRISTENSEN
Footing/Foundation/Slab 12/1/2025 Approved CHRIS CHRISTENSEN
Underground Mechanical 12/1/2025 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 12/17/2025 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 12/17/2025 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Rough 12/17/2025 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Rough 12/17/2025 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 12/17/2025 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 12/18/2025 Approved CHRIS CHRISTENSEN
HVAC-Rough 12/18/2025 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 12/18/2025 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 12/30/2025 Approved CHRIS CHRISTENSEN
Green Building Rough 12/30/2025 Approved CHRIS CHRISTENSEN
Insulation 12/30/2025 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 12/30/2025 Partial Approval CHRIS CHRISTENSEN
Interior/Exterior Lathing 2/3/2026 Partial Approval CHRIS CHRISTENSEN
Shower Pan 2/3/2026 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 2/9/2026 Not Ready for Inspection CHRIS CHRISTENSEN
Drywall Nailing 2/19/2026 Approved KRISTEN CAUSEY
Final 4/8/2026 Corrections Issued JEFFREY HARTLINE
Green Building Final 4/8/2026 Not Ready for Inspection JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 4/8/2026 SGSOV Not Ready JEFFREY HARTLINE
Smoke Detectors 4/8/2026 Approved JEFFREY HARTLINE
Final 4/13/2026 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 4/13/2026 Not Ready for Inspection CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 4/13/2026 SGSOV Approved CHRIS CHRISTENSEN
Final 4/15/2026 OK to Issue CofO CHRIS CHRISTENSEN
Green Building Final 4/15/2026 Approved CHRIS CHRISTENSEN