14636-14638 W MARTHA ST 91411

Certificate Information: 14636-14638 W MARTHA ST 91411

Application / Permit
25016-20000-27801
Plan Check / Job No.
B25VN26963
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
SEPERATE (E) SFD INTO IRREGULAR SHAPE ( 49'-11" X 40'-6") SB9 PER per SB9 Two-Unit Development Ca Govt Code 65852.21 AND IRREGULAR SHAPE (85'-1" X 31'-4") SFD.
Permit Issued
Issued on 10/22/2025
Issuing Office
Current Status
CofO Issued on 7/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/15/2025 APPLICANT
Assigned to Plan Check Engineer 9/18/2025 EDWARD MEHRABIAN
Assigned to Zoning Architect 9/18/2025 SHARAREH KAHENASSA
Corrections Issued 9/25/2025 EDWARD MEHRABIAN
Quality Review Completed 9/26/2025 OMID HEDAYAT
Building Plans Picked Up 9/26/2025 APPLICANT
Applicant returned to address corrections 9/30/2025 EDWARD MEHRABIAN
Plan Check Approved 10/22/2025 EDWARD MEHRABIAN
Issued 10/22/2025 APPLICANT
CofO in Progress 5/22/2026 VINCENT HANLEY
Permit Finaled 7/2/2026 RUBEN SALAS
CofO Issued 7/2/2026 RUBEN SALAS
Permit Finaled 7/2/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/25/2025 MICHAEL BROWN
Senate Bill 9 Cleared 9/30/2025 ROSALINDA MEZA
Eng Process Fee Ord 176,300 Cleared 10/6/2025 MICHAEL BROWN
Sewer availability Cleared 10/6/2025 MICHAEL BROWN
Zoning Plan Check Cleared 10/16/2025 SHARAREH KAHENASSA

Contact Information

Contractor Az Vision Remodeling; Lic. No.: 1015050-B 11909 TIARA STREET      VALLEY VILLAGE, CA 91607
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/24/2025 Conditional Approval JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 10/28/2025 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 11/18/2025 Corrections Issued MISAEL ESPARZA
Interior/Exterior Lathing 11/18/2025 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 11/18/2025 Corrections Issued MISAEL ESPARZA
Shower Pan 12/8/2025 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 12/10/2025 Not Ready for Inspection RYAN SALAZAR
ELECTRICAL-Rough 12/10/2025 Conditional Approval RYAN SALAZAR
HVAC-Rough 12/10/2025 Conditional Approval RYAN SALAZAR
Insulation 12/10/2025 Not Ready for Inspection RYAN SALAZAR
PLUMBING-Rough 12/10/2025 Conditional Approval RYAN SALAZAR
Insulation 12/18/2025 Approved RYAN SALAZAR
Drywall Nailing 12/29/2025 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 12/29/2025 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 2/10/2026 Partial Approval KIRK SANDERS
BUILDING-Rough-Frame 3/20/2026 Not Ready for Inspection VINCENT HANLEY
Final 3/20/2026 Not Ready for Inspection VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 3/20/2026 SGSOV Approved VINCENT HANLEY
Special/Order Compliance 3/20/2026 Corrections Issued VINCENT HANLEY
Special/Order Compliance 3/20/2026 Partial Inspection JOSE AVILA
BUILDING-Rough-Frame 4/9/2026 No Access for Inspection VINCENT HANLEY
Final 4/9/2026 No Access for Inspection VINCENT HANLEY
Smoke Detectors 4/9/2026 No Access for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 4/13/2026 Approved VINCENT HANLEY
ELECTRICAL-Final 4/13/2026 Approved VINCENT HANLEY
Final 4/13/2026 Corrections Issued VINCENT HANLEY
HVAC-Final 4/13/2026 Corrections Issued VINCENT HANLEY
PLUMBING-Final 4/13/2026 Approved VINCENT HANLEY
Service/Power Release 4/13/2026 Approved VINCENT HANLEY
Smoke Detectors 4/13/2026 Approved VINCENT HANLEY
Final 4/24/2026 Corrections Issued VINCENT HANLEY
Final 5/21/2026 OK to Issue CofO VINCENT HANLEY
HVAC-Final 5/21/2026 Approved VINCENT HANLEY