1535 N MOHAWK ST 90026

Certificate Information: 1535 N MOHAWK ST 90026

Application / Permit
25016-20000-27406
Plan Check / Job No.
B25VN26537
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE EXISTING SINGLE FAMILY DWELLING AND ATTACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER GC 66323(a)(1). RE-FRAME ENTIRE ROOF OF STRUCTURE. ALL WORK DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 9/29/2025
Issuing Office
Valley
Current Status
Issued on 9/29/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/10/2025 APPLICANT
Assigned to Plan Check Engineer 9/15/2025 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 9/15/2025 SEWADA ZADOORIAN MILAGARDI
Building Plans Picked Up 9/18/2025 APPLICANT
Applicant returned to address corrections 9/23/2025 PINANK PATEL
Plan Check Approved 9/29/2025 ANGELICA DAVE
Issued 9/29/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/26/2025 JEFF LOREDO
Roof/Waste drainage to street Cleared 9/26/2025 JEFF LOREDO
Sewer availability Cleared 9/26/2025 JEFF LOREDO
Eng Process Fee Ord 176,300 Cleared 9/29/2025 JEFF LOREDO
Grading Pre-Inspection Cleared 9/29/2025 CHARLES POWELL

Contact Information

Contractor Tri Tech Restoration & Co; Lic. No.: 501801-B 3301 N SAN FERNANDO BLVD      BURBANK, CA 91504
Engineer Manoukian,, Krikor Kerop; Lic. No.: C87010 2310 W MAGNOLIA BLVD STE A      BURBANK, CA 91506

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/12/2025 Conditional Approval ANTHONY RAMOS
Excavation/Setback/Form/Re-Bar 11/18/2025 Partial Inspection WILLIAM SIERRA
Footing/Foundation/Slab 11/18/2025 Corrections Issued WILLIAM SIERRA
Footing/Foundation/Slab 12/5/2025 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 12/9/2025 Approved HAMIK HARTOUNIAN
Deputy Drilled-In Anchors 1/28/2026 Conditional Approval OSVALDO PARAMO
Deputy Drilled-In Anchors 3/31/2026 Conditional Approval HAMIK HARTOUNIAN
Wood Frame 4/15/2026 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 4/17/2026 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 4/28/2026 Approved HAMIK HARTOUNIAN
Green Building Rough 4/28/2026 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 5/15/2026 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 5/15/2026 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 5/15/2026 Approved HAMIK HARTOUNIAN
Deputy Wood Construction 5/18/2026 Conditional Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 5/19/2026 Not Ready for Inspection HAMIK HARTOUNIAN