8929 W MULBERRY DR 91040
Certificate Information: 8929 W MULBERRY DR 91040
- Application / Permit
- 25016-20000-27391
- Plan Check / Job No.
- B25VN26511
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: INTERIOR REMODEL AND NEW BATHROOM ADDITION WITHIN SFD
- Permit Issued
- Issued on 9/24/2025
- Issuing Office
- Current Status
- Permit Finaled on 1/22/2026
Permit Application Status History
| Submitted | 9/10/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/15/2025 | ARAMIK SHAHMIRZAIAN |
| Corrections Issued | 9/16/2025 | ARAMIK SHAHMIRZAIAN |
| Plan Check Approved | 9/19/2025 | ARAMIK SHAHMIRZAIAN |
| Issued | 9/24/2025 | APPLICANT |
| Permit Finaled | 1/21/2026 | NICHOLAS TROWBRIDGE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/17/2025 | ALEXANDER HELFER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Bogossian,, Oshin; Lic. No.: C78191 | 6518 GREELEY ST TUJUNGA, CA 91042 |
| Engineer | Bogossian,, Oshin; Lic. No.: NA78191 | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/12/2025 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 11/14/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 11/14/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Footing/Foundation/Slab | 11/14/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Gas Test | 11/14/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| HVAC-Rough | 11/14/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 11/14/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Special/Order Compliance | 11/14/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Underground Mechanical | 11/14/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Wood Frame | 11/14/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 11/19/2025 | Corrections Issued | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 11/19/2025 | Approved | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 11/19/2025 | Approved | KEVIN BERBERYAN |
| Gas Test | 11/19/2025 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 11/19/2025 | Corrections Issued | KEVIN BERBERYAN |
| PLUMBING-Rough | 11/19/2025 | Approved | KEVIN BERBERYAN |
| Sewer | 11/19/2025 | Approved | KEVIN BERBERYAN |
| Wood Frame | 11/19/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 11/25/2025 | Approved | NICHOLAS TROWBRIDGE |
| HVAC-Rough | 11/25/2025 | Approved | NICHOLAS TROWBRIDGE |
| Insulation | 11/25/2025 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 11/25/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Shower Pan | 11/25/2025 | Approved | NICHOLAS TROWBRIDGE |
| Drywall Nailing | 12/2/2025 | Approved | DAVID MATSON |
| Interior/Exterior Lathing | 12/2/2025 | Partial Approval | DAVID MATSON |
| Interior/Exterior Lathing | 12/5/2025 | Approved | MICHAEL CORTEZ |
| ELECTRICAL-Final | 1/21/2026 | Approved | NICHOLAS TROWBRIDGE |
| Final | 1/21/2026 | Permit Finaled | NICHOLAS TROWBRIDGE |
| HVAC-Final | 1/21/2026 | Approved | NICHOLAS TROWBRIDGE |
| PLUMBING-Final | 1/21/2026 | Approved | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 1/21/2026 | SGSOV Approved | NICHOLAS TROWBRIDGE |
| Service/Power Release | 1/21/2026 | Approved | NICHOLAS TROWBRIDGE |
| Smoke Detectors | 1/21/2026 | Approved | NICHOLAS TROWBRIDGE |