10330 N BEVIS AVE 91345
Certificate Information: 10330 N BEVIS AVE 91345
- Application / Permit
- 25016-20000-27209
- Plan Check / Job No.
- B25VN26315
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REPLACE ROOF FRAMING FOR EX. SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 10/8/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/5/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/9/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/15/2025 | JESSE ARELLANO |
| Corrections Issued | 9/16/2025 | JESSE ARELLANO |
| Building Plans Picked Up | 9/17/2025 | APPLICANT |
| Plan Check Approved | 10/1/2025 | ROSENDO MEDINA |
| Issued | 10/8/2025 | APPLICANT |
| CofO in Progress | 1/30/2026 | JENNIFER RABUCHIN |
| Permit Finaled | 3/5/2026 | RUBEN SALAS |
| CofO Issued | 3/5/2026 | RUBEN SALAS |
| Permit Finaled | 3/5/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/29/2025 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/30/2025 | DAVID LOPEZ |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: C23963 | 6320 VAN NUYS BOULEVARD #225 VAN NUYS, CA 91401 |
| Contractor | Rafael Builders; Lic. No.: 1132908-C39 | 5458 SILVIA AVE TARZANA, CA 91356 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2025 | No Access for Inspection | JENNIFER RABUCHIN |
| Pre-Inspection | 10/15/2025 | Partial Inspection | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 10/30/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 10/30/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 10/30/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 11/7/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2025 | Approved | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 11/13/2025 | Partial Approval | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 1/5/2026 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 1/14/2026 | Approved | JENNIFER RABUCHIN |
| Final | 1/14/2026 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 1/14/2026 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 1/14/2026 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 1/30/2026 | Approved | JENNIFER RABUCHIN |
| Final | 1/30/2026 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 1/30/2026 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 1/30/2026 | Approved | JENNIFER RABUCHIN |