11317-11319 W ROSE AVE 90066
Certificate Information: 11317-11319 W ROSE AVE 90066
- Application / Permit
- 25016-20000-27197
- Plan Check / Job No.
- B25VN26305
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 66323(a)(1) AND INTERIOR/EXTERIOR REMODEL TO (E) SFD.
- Permit Issued
- Issued on 10/15/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/22/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/9/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/12/2025 | JESSE ARELLANO |
| Corrections Issued | 9/13/2025 | JESSE ARELLANO |
| Building Plans Picked Up | 9/15/2025 | APPLICANT |
| Plan Check Approved | 10/10/2025 | GURUNATH NESARAJAH |
| Issued | 10/15/2025 | APPLICANT |
| CofO in Progress | 5/22/2026 | ARAM AVEDISIAN |
| Permit Finaled | 5/22/2026 | RICHARD STEINBACH |
| CofO Issued | 5/22/2026 | RICHARD STEINBACH |
| Permit Finaled | 5/22/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 9/22/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 9/22/2025 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 9/22/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 9/22/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 9/22/2025 | LEE GUILBEAUX |
| Grading Pre-Inspection | Cleared | 10/1/2025 | LANNY MERRICK |
| Hold | Cleared | 10/15/2025 | MARIA VENDIVIL |
Contact Information
| Contractor | Brooktree Construction; Lic. No.: 1111295-B | 7427 WOODLEY AVENUE VAN NUYS, CA 91406 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/16/2025 | Conditional Approval | KIRK SANDERS |
| Footing/Foundation/Slab | 10/17/2025 | Corrections Issued | KIRK SANDERS |
| Excavation/Setback/Form/Re-Bar | 10/21/2025 | Approved | WILBER ROSALES |
| BUILDING-Rough-Frame | 10/24/2025 | Not Ready for Inspection | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2025 | Partial Approval | KIRK SANDERS |
| Green Building Rough | 10/24/2025 | Not Ready for Inspection | KIRK SANDERS |
| MERV13>=Rough | 10/24/2025 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Rough | 12/10/2025 | Corrections Issued | MICHAEL ALLEN |
| HVAC-Rough | 12/10/2025 | Corrections Issued | MICHAEL ALLEN |
| PLUMBING-Rough | 12/10/2025 | Approved | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 12/12/2025 | Not Ready for Inspection | KIRK SANDERS |
| Green Building Rough | 12/12/2025 | Not Ready for Inspection | KIRK SANDERS |
| MERV13>=Rough | 12/12/2025 | Not Ready for Inspection | KIRK SANDERS |
| BUILDING-Rough-Frame | 1/16/2026 | Partial Approval | KIRK SANDERS |
| ELECTRICAL-Rough | 1/16/2026 | Approved | KIRK SANDERS |
| HVAC-Rough | 1/16/2026 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 1/16/2026 | Partial Approval | KIRK SANDERS |
| PLUMBING-Rough | 1/16/2026 | Approved | KIRK SANDERS |
| Insulation | 1/23/2026 | Approved | ARAM AVEDISIAN |
| Shower Pan | 1/23/2026 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 1/28/2026 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 1/28/2026 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Final | 4/23/2026 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Final | 4/23/2026 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Final | 4/30/2026 | Corrections Issued | EVAN COOPER |
| HVAC-Final | 4/30/2026 | Corrections Issued | EVAN COOPER |
| PLUMBING-Final | 4/30/2026 | Corrections Issued | EVAN COOPER |
| BUILDING-Rough-Frame | 5/21/2026 | Approved | ARAM AVEDISIAN |
| Final | 5/21/2026 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 5/21/2026 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 5/21/2026 | Approved | ARAM AVEDISIAN |
| MERV13>=Final | 5/21/2026 | Approved | ARAM AVEDISIAN |
| MERV13>=Rough | 5/21/2026 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 5/21/2026 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 5/21/2026 | Approved | ARAM AVEDISIAN |
| Final | 5/22/2026 | OK to Issue CofO | ARAM AVEDISIAN |
| Service/Power Release | 5/22/2026 | Approved | ARAM AVEDISIAN |