13870-13872 N STRATTON AVE 91342
Certificate Information: 13870-13872 N STRATTON AVE 91342
- Application / Permit
- 25016-20000-26913
- Plan Check / Job No.
- B25VN25995
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan: Convert (E) attached two car garage in to (N) ADU per GC 66323(a)(1)
- Permit Issued
- Issued on 10/20/2025
- Issuing Office
- Current Status
- CofO Issued on 6/24/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/7/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/11/2025 | KAVIAN REFAHI |
| Corrections Issued | 9/14/2025 | KAVIAN REFAHI |
| Plan Check Approved | 10/19/2025 | KAVIAN REFAHI |
| Issued | 10/20/2025 | APPLICANT |
| CofO in Progress | 6/15/2026 | KEVIN BERBERYAN |
| CofO Issued | 6/24/2026 | RUBEN SALAS |
| Permit Finaled | 6/24/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/22/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 9/22/2025 | STEVE MELGAR |
| Sewer availability | Cleared | 9/22/2025 | STEVE MELGAR |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/13/2025 | Partial Approval | KEVIN BERBERYAN |
| Sewer | 11/13/2025 | Approved | KEVIN BERBERYAN |
| Deputy Drilled-In Anchors | 11/25/2025 | Conditional Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 11/26/2025 | Corrections Issued | KEVIN BERBERYAN |
| Wood Frame | 12/15/2025 | Partial Approval | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 1/6/2026 | Corrections Issued | KEVIN BERBERYAN |
| HVAC-Rough | 1/6/2026 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 1/6/2026 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 1/12/2026 | Approved | KEVIN BERBERYAN |
| Insulation | 1/12/2026 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 1/14/2026 | Approved | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/14/2026 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 1/28/2026 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 1/28/2026 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Final | 4/9/2026 | Corrections Issued | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 5/19/2026 | Approved | KEVIN BERBERYAN |
| Final | 5/19/2026 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 5/19/2026 | Not Ready for Inspection | KEVIN BERBERYAN |
| Green Building Rough | 5/19/2026 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 5/19/2026 | SGSOV No Gas | KEVIN BERBERYAN |
| Service/Power Release | 5/19/2026 | Approved | KEVIN BERBERYAN |
| Smoke Detectors | 5/19/2026 | Approved | KEVIN BERBERYAN |
| Final | 6/15/2026 | OK to Issue CofO | KEVIN BERBERYAN |
| Green Building Final | 6/15/2026 | Approved | KEVIN BERBERYAN |