9774 W MILLBORO PL 90210
Certificate Information: 9774 W MILLBORO PL 90210
- Application / Permit
- 25016-20000-26854
- Plan Check / Job No.
- B25VN25917
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO EXISTING SINGLE FAMILY DWELLING WITH ATTACHED GARAGE
- Permit Issued
- Issued on 10/14/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 10/14/2025
Permit Application Status History
| Submitted | 9/5/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/11/2025 | SELLA BENYAMIN |
| Assigned to Zoning Architect | 9/11/2025 | HAYDON CHAN |
| Corrections Issued | 9/16/2025 | SELLA BENYAMIN |
| Quality Review Completed | 9/17/2025 | STEVEN KIM |
| Building Plans Picked Up | 9/18/2025 | APPLICANT |
| Plan Check Approved | 10/7/2025 | SELLA BENYAMIN |
| Issued | 10/14/2025 | APPLICANT |
Permit Application Clearance Information
| Zoning Plan Check | Cleared | 9/30/2025 | HAYDON CHAN |
Contact Information
| Contractor | Slater Construction And Development Inc; Lic. No.: 339608-B | 200 S BARRINGTON AVE 1486 LOS ANGELES, CA 90049 |
| Engineer | Reith,, David Lee; Lic. No.: C72122 | 1319 FEATHER AVE THOUSAND OAKS, CA 91360 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/22/2025 | Approved | CARLOS MATAMOROS |
| Deputy Steel/Welding | 1/22/2026 | Conditional Approval | ANDREW NAVE |
| Deputy Steel/Welding | 1/23/2026 | Conditional Approval | ANDREW NAVE |
| Interior/Exterior Lathing | 2/24/2026 | Partial Approval | CARLOS MATAMOROS |
| PLUMBING-Rough | 2/24/2026 | Partial Approval | CARLOS MATAMOROS |
| Underground Mechanical | 2/24/2026 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 4/7/2026 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 4/7/2026 | Corrections Issued | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 4/7/2026 | Partial Approval | CARLOS MATAMOROS |
| PLUMBING-Rough | 4/7/2026 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 4/10/2026 | Conditional Approval | CARLOS MATAMOROS |
| Wood Frame | 4/10/2026 | Conditional Approval | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 4/15/2026 | Approved | CARLOS MATAMOROS |
| Deputy Wood Construction | 4/15/2026 | Conditional Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2026 | Approved | CARLOS MATAMOROS |
| Insulation | 4/15/2026 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 4/23/2026 | Approved | CARLOS MATAMOROS |
| Shower Pan | 4/23/2026 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 4/28/2026 | Approved | CARLOS MATAMOROS |