11159 W SARAH ST 91602
Certificate Information: 11159 W SARAH ST 91602
- Application / Permit
- 25016-20000-26504
- Plan Check / Job No.
- B25VN25573
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. Convert existing detached garage (564 SF) to ADU per State Law.
- Permit Issued
- Issued on 10/4/2025
- Issuing Office
- Current Status
- CofO in Progress on 4/29/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/5/2025 | EDWIN MARTINEZ |
| Corrections Issued | 9/7/2025 | EDWIN MARTINEZ |
| Plan Check Approved | 9/23/2025 | DANIEL SMILEY |
| Issued | 10/4/2025 | APPLICANT |
| CofO in Progress | 4/29/2026 | JAVIER RAMOS JR |
Permit Application Clearance Information
| Address approval | Cleared | 9/15/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 9/15/2025 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 9/16/2025 | MICHAEL BROWN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Test | 1/14/2026 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 1/14/2026 | Approved | JAVIER RAMOS JR |
| Sewer | 1/14/2026 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 1/14/2026 | Partial Approval | JAVIER RAMOS JR |
| Pre-Inspection | 2/10/2026 | Partial Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 2/20/2026 | Approved | JAVIER RAMOS JR |
| Pre-Inspection | 2/20/2026 | Partial Approval | JAVIER RAMOS JR |
| Wood Frame | 2/25/2026 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 3/2/2026 | Corrections Issued | GAREN HAYRAPETYAN |
| HVAC-Rough | 3/2/2026 | Corrections Issued | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 3/4/2026 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 3/4/2026 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 3/10/2026 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2026 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 3/10/2026 | Approved | JAVIER RAMOS JR |
| MERV13>=Rough | 3/10/2026 | Approved | JAVIER RAMOS JR |
| Wood Frame | 3/10/2026 | Approved | JAVIER RAMOS JR |
| Insulation | 3/11/2026 | Corrections Issued | JAVIER RAMOS JR |
| Drywall Nailing | 3/12/2026 | Partial Approval | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 3/17/2026 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 4/1/2026 | Approved | JAVIER RAMOS JR |
| Shower Pan | 4/1/2026 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 4/23/2026 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 4/23/2026 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 4/23/2026 | Approved | JAVIER RAMOS JR |
| Smoke Detectors | 4/23/2026 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 4/24/2026 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 4/24/2026 | Approved | JAVIER RAMOS JR |
| Final | 4/24/2026 | Partial Inspection | JAVIER RAMOS JR |
| Green Building Final | 4/24/2026 | Approved | JAVIER RAMOS JR |
| Insulation | 4/24/2026 | Approved | JAVIER RAMOS JR |
| MERV13>=Final | 4/24/2026 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 4/24/2026 | SGSOV Approved | JAVIER RAMOS JR |
| Final | 4/29/2026 | OK to Issue CofO | JAVIER RAMOS JR |