18323 W KINZIE ST 91325

Certificate Information: 18323 W KINZIE ST 91325

Application / Permit
25016-20000-26488
Plan Check / Job No.
B25VN25562
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED ACCESSORY LIVING QUARTERS TO ACCESSORY DWELLING UNIT PER GCS 66323(a)(1).
Permit Issued
Issued on 2/18/2026
Issuing Office
Current Status
CofO Issued on 7/10/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/2/2025 APPLICANT
Assigned to Plan Check Engineer 9/8/2025 ARTIN ZARUKIAN
Corrections Issued 9/9/2025 ARTIN ZARUKIAN
Building Plans Picked Up 9/18/2025 APPLICANT
Plan Check Approved 2/10/2026 ALEC MOUSAKHANIAN
Issued 2/18/2026 APPLICANT
CofO in Progress 6/26/2026 JACK KARGODORIAN
Permit Finaled 7/10/2026 JOHN JANSON
CofO Issued 7/10/2026 JOHN JANSON
Permit Finaled 7/10/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 9/12/2025 MICHAEL BROWN
Eng Process Fee Ord 176,300 Cleared 9/12/2025 MICHAEL BROWN
Sewer availability Cleared 9/12/2025 MICHAEL BROWN
Construction near power lines Cleared 12/5/2025 GEVORK KARAPETYAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/13/2026 Approved DAVID SCANTLIN
Interior/Exterior Lathing 3/13/2026 Partial Approval DAVID SCANTLIN
BUILDING-Rough-Frame 3/31/2026 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Rough 3/31/2026 Corrections Issued DAVID SCANTLIN
Green Building Rough 3/31/2026 Approved DAVID SCANTLIN
HVAC-Rough 3/31/2026 Not Ready for Inspection DAVID SCANTLIN
PLUMBING-Rough 3/31/2026 Approved DAVID SCANTLIN
ELECTRICAL-Rough 4/3/2026 Corrections Issued HENRY KIM
HVAC-Rough 4/3/2026 Approved HENRY KIM
ELECTRICAL-Rough 4/7/2026 Approved DAVID SCANTLIN
Insulation 4/10/2026 Approved DAVID SCANTLIN
Drywall Nailing 4/20/2026 Approved JEFFREY PARD
BUILDING-Rough-Frame 5/19/2026 Approved JACK KARGODORIAN
Final 5/19/2026 Corrections Issued JACK KARGODORIAN
Green Building Final 5/19/2026 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 5/19/2026 SGSOV Approved JACK KARGODORIAN
Smoke Detectors 5/19/2026 Approved JACK KARGODORIAN
Final 5/28/2026 Corrections Issued HENRY KIM
Final 6/25/2026 OK to Issue CofO JACK KARGODORIAN