11055-11057 N RUFFNER AVE 91344

Certificate Information: 11055-11057 N RUFFNER AVE 91344

Application / Permit
25016-20000-26466
Plan Check / Job No.
B25VN25543
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan: Convert existing attached two-car garage to Accessory Dwelling Unit (ADU) in existing single family dwelling per WFPP
Permit Issued
Issued on 9/15/2025
Issuing Office
Current Status
CofO Issued on 7/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/3/2025 APPLICANT
Assigned to Plan Check Engineer 9/5/2025 NEHEMIAS RAMOS
Corrections Issued 9/6/2025 NEHEMIAS RAMOS
Plan Check Approved 9/14/2025 NEHEMIAS RAMOS
Issued 9/15/2025 APPLICANT
CofO in Progress 6/30/2026 CHRISTOPHER ROJAS
CofO Issued 7/9/2026 RUBEN SALAS
Permit Finaled 7/9/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/10/2025 SAFA JAVANMARDI
Sewer availability Cleared 9/10/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 9/11/2025 SAFA JAVANMARDI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 1/15/2026 Corrections Issued CHRISTOPHER ROJAS
Excavation/Setback/Form/Re-Bar 1/22/2026 Partial Approval CHRISTOPHER ROJAS
Footing/Foundation/Slab 1/22/2026 Partial Approval CHRISTOPHER ROJAS
Sewer 1/22/2026 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 2/10/2026 Partial Approval KIRK SANDERS
PLUMBING-Rough 2/10/2026 Partial Approval KIRK SANDERS
BUILDING-Rough-Frame 3/19/2026 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 3/19/2026 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 3/19/2026 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 3/19/2026 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Rough 3/19/2026 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 3/27/2026 Approved CHRISTOPHER ROJAS
HVAC-Rough 3/27/2026 Approved CHRISTOPHER ROJAS
Insulation 3/27/2026 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 3/27/2026 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 4/23/2026 Approved KEVIN BERBERYAN
Drywall Nailing 4/30/2026 Corrections Issued CHRISTOPHER ROJAS
Interior/Exterior Lathing 4/30/2026 Partial Approval CHRISTOPHER ROJAS
Drywall Nailing 5/8/2026 Approved CHRISTOPHER ROJAS
Shower Pan 5/8/2026 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 6/16/2026 Corrections Issued CHRISTOPHER ROJAS
Final 6/16/2026 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Final 6/16/2026 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Final 6/16/2026 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 6/16/2026 SGSOV Not Ready CHRISTOPHER ROJAS
Smoke Detectors 6/16/2026 Approved CHRISTOPHER ROJAS
Final 6/22/2026 Corrections Issued KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 6/22/2026 SGSOV Approved KEVIN BERBERYAN
Final 6/29/2026 OK to Issue CofO CHRISTOPHER ROJAS