11055-11057 N RUFFNER AVE 91344
Certificate Information: 11055-11057 N RUFFNER AVE 91344
- Application / Permit
- 25016-20000-26466
- Plan Check / Job No.
- B25VN25543
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan: Convert existing attached two-car garage to Accessory Dwelling Unit (ADU) in existing single family dwelling per WFPP
- Permit Issued
- Issued on 9/15/2025
- Issuing Office
- Current Status
- CofO Issued on 7/9/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/5/2025 | NEHEMIAS RAMOS |
| Corrections Issued | 9/6/2025 | NEHEMIAS RAMOS |
| Plan Check Approved | 9/14/2025 | NEHEMIAS RAMOS |
| Issued | 9/15/2025 | APPLICANT |
| CofO in Progress | 6/30/2026 | CHRISTOPHER ROJAS |
| CofO Issued | 7/9/2026 | RUBEN SALAS |
| Permit Finaled | 7/9/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/10/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 9/10/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 9/11/2025 | SAFA JAVANMARDI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 1/15/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Excavation/Setback/Form/Re-Bar | 1/22/2026 | Partial Approval | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 1/22/2026 | Partial Approval | CHRISTOPHER ROJAS |
| Sewer | 1/22/2026 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 2/10/2026 | Partial Approval | KIRK SANDERS |
| PLUMBING-Rough | 2/10/2026 | Partial Approval | KIRK SANDERS |
| BUILDING-Rough-Frame | 3/19/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 3/19/2026 | Approved | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| HVAC-Rough | 3/19/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 3/19/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 3/27/2026 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 3/27/2026 | Approved | CHRISTOPHER ROJAS |
| Insulation | 3/27/2026 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 3/27/2026 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 4/23/2026 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 4/30/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 4/30/2026 | Partial Approval | CHRISTOPHER ROJAS |
| Drywall Nailing | 5/8/2026 | Approved | CHRISTOPHER ROJAS |
| Shower Pan | 5/8/2026 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 6/16/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 6/16/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| HVAC-Final | 6/16/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Final | 6/16/2026 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 6/16/2026 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Smoke Detectors | 6/16/2026 | Approved | CHRISTOPHER ROJAS |
| Final | 6/22/2026 | Corrections Issued | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 6/22/2026 | SGSOV Approved | KEVIN BERBERYAN |
| Final | 6/29/2026 | OK to Issue CofO | CHRISTOPHER ROJAS |