17613 W KITTRIDGE ST 91406
Certificate Information: 17613 W KITTRIDGE ST 91406
- Application / Permit
- 25016-20000-26341
- Plan Check / Job No.
- B25VN25402
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE AND RECROOM WITH ACCESSORY DWELLIING UNIT PER GC 66323(a)(1).
- Permit Issued
- Issued on 1/22/2026
- Issuing Office
- Current Status
- Issued on 1/22/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/5/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2025 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 9/9/2025 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 1/8/2026 | MOHAMMAD ESMAILI |
| Plan Check Approved | 1/21/2026 | MOHAMMAD ESMAILI |
| Issued | 1/22/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/18/2025 | TONY CHIANG |
| Eng Process Fee Ord 176,300 | Cleared | 9/18/2025 | TONY CHIANG |
| Sewer availability | Cleared | 9/18/2025 | TONY CHIANG |
| Construction near power lines | Cleared | 10/29/2025 | GEVORK KARAPETYAN |
| Construction within easement | Cleared | 10/29/2025 | GEVORK KARAPETYAN |
Contact Information
| Contractor | Omni Medical Construction Inc; Lic. No.: 1030850-B | , |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 3600 WILSHIRE BLVD STE 1903 LOS ANGELES, CA 90010 |
| Engineer | Kim,, Hong Kook; Lic. No.: NA64529 | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/20/2026 | Not Ready for Inspection | MORRIS JACKSON |
| Footing/Foundation/Slab | 2/20/2026 | Corrections Issued | MORRIS JACKSON |
| Sewer | 2/20/2026 | Not Ready for Inspection | MORRIS JACKSON |
| Underground Mechanical | 2/20/2026 | Not Ready for Inspection | MORRIS JACKSON |
| PLUMBING-Rough | 2/25/2026 | Partial Approval | MORRIS JACKSON |
| Sewer | 2/25/2026 | Not Ready for Inspection | MORRIS JACKSON |
| Excavation/Setback/Form/Re-Bar | 2/27/2026 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 3/31/2026 | Corrections Issued | MORRIS JACKSON |
| ELECTRICAL-Rough | 3/31/2026 | Corrections Issued | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2026 | Partial Approval | MORRIS JACKSON |
| Gas Test | 3/31/2026 | Approved | MORRIS JACKSON |
| Green Building Rough | 3/31/2026 | Not Ready for Inspection | MORRIS JACKSON |
| HVAC-Rough | 3/31/2026 | Corrections Issued | MORRIS JACKSON |
| PLUMBING-Rough | 3/31/2026 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 4/8/2026 | Corrections Issued | MORRIS JACKSON |
| ELECTRICAL-Rough | 4/8/2026 | Approved | MORRIS JACKSON |
| Green Building Rough | 4/8/2026 | Approved | MORRIS JACKSON |
| HVAC-Rough | 4/8/2026 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 4/8/2026 | Partial Approval | MORRIS JACKSON |
| BUILDING-Rough-Frame | 4/10/2026 | Partial Approval | MORRIS JACKSON |
| ELECTRICAL-Rough | 4/10/2026 | Approved | MORRIS JACKSON |
| HVAC-Rough | 4/10/2026 | Approved | MORRIS JACKSON |
| MERV13>=Rough | 4/10/2026 | Approved | MORRIS JACKSON |
| PLUMBING-Rough | 4/10/2026 | Approved | MORRIS JACKSON |
| Rough-Elec/Plmb/HVAC | 4/10/2026 | Approved | MORRIS JACKSON |
| Shower Pan | 4/10/2026 | Approved | MORRIS JACKSON |
| Insulation | 4/13/2026 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 4/13/2026 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 4/15/2026 | Approved | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2026 | Partial Approval | MORRIS JACKSON |
| Green Building Rough | 4/15/2026 | Approved | MORRIS JACKSON |
| Drywall Nailing | 4/17/2026 | Approved | JON MCHUGH |
| Gas Test | 6/11/2026 | Approved | IVAN SARABIA |
| Special/Order Compliance | 6/11/2026 | Partial Inspection | ROBERT GOLD |
| Final | 7/14/2026 | Corrections Issued | JON MCHUGH |
| Green Building Final | 7/14/2026 | Not Ready for Inspection | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 7/14/2026 | SGSOV Not Ready | JON MCHUGH |
| Smoke Detectors | 7/14/2026 | Approved | JON MCHUGH |