6257 N PEACH AVE 91411
Certificate Information: 6257 N PEACH AVE 91411
- Application / Permit
- 25016-20000-26087
- Plan Check / Job No.
- B25VN25123
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GC 66323(a)(1). WORK PER ENGINEERED DESIGN.
- Permit Issued
- Issued on 9/4/2025
- Issuing Office
- Current Status
- CofO Issued on 1/8/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/28/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/3/2025 | OMAR GARNICA |
| Corrections Issued | 9/3/2025 | OMAR GARNICA |
| Building Plans Picked Up | 9/3/2025 | APPLICANT |
| Issued | 9/4/2025 | APPLICANT |
| CofO in Progress | 12/22/2025 | RYAN SALAZAR |
| Permit Finaled | 1/8/2026 | RUBEN SALAS |
| CofO Issued | 1/8/2026 | RUBEN SALAS |
| Permit Finaled | 1/8/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/3/2025 | DERRICK MAGEE |
| Eng Process Fee Ord 176,300 | Cleared | 9/3/2025 | CARLOS AGUILERA |
| Sewer availability | Cleared | 9/3/2025 | DERRICK MAGEE |
Contact Information
| Contractor | Centrepoint Construction Inc; Lic. No.: 1032400-B | 21101 VICTORY BLVD STE 225 CANOGA PARK, CA 91303 |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/29/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 9/29/2025 | Partial Approval | RYAN SALAZAR |
| Sewer | 9/29/2025 | Approved | RYAN SALAZAR |
| Underground Mechanical | 9/29/2025 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 10/21/2025 | Approved | RYAN SALAZAR |
| Green Building Rough | 10/21/2025 | Approved | RYAN SALAZAR |
| Rough-Elec/Plmb/HVAC | 10/21/2025 | Approved | RYAN SALAZAR |
| Insulation | 10/30/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 10/30/2025 | Partial Approval | RYAN SALAZAR |
| Shower Pan | 10/30/2025 | Approved | RYAN SALAZAR |
| Drywall Nailing | 11/5/2025 | Corrections Issued | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 11/5/2025 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 11/7/2025 | Approved | JACK KARGODORIAN |
| Final | 12/16/2025 | OK to Issue CofO | RYAN SALAZAR |
| Green Building Final | 12/16/2025 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 12/16/2025 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 12/16/2025 | Approved | RYAN SALAZAR |