7301-7303 N CASABA AVE 91306

Certificate Information: 7301-7303 N CASABA AVE 91306

Application / Permit
25016-20000-25959
Plan Check / Job No.
B25VN24991
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER GC 66323(a)(1).
Permit Issued
Issued on 9/11/2025
Issuing Office
Valley
Current Status
Issued on 9/11/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/27/2025 APPLICANT
Assigned to Plan Check Engineer 9/3/2025 ISIS ARGUETA
Corrections Issued 9/3/2025 ISIS ARGUETA
Building Plans Picked Up 9/4/2025 APPLICANT
Plan Check Approved 9/11/2025 YAQUB MIRZA
Issued 9/11/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/9/2025 BIAINA HARITUNIAN
Sewer availability Cleared 9/9/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 9/10/2025 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/26/2025 Partial Inspection HENRY KIM
Excavation/Setback/Form/Re-Bar 10/28/2025 Approved ALEXANDER HANDY
Footing/Foundation/Slab 10/28/2025 Approved ALEXANDER HANDY
PLUMBING-Rough 10/28/2025 Partial Approval ALEXANDER HANDY
Sewer 10/28/2025 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 12/23/2025 Corrections Issued ALEXANDER HANDY
ELECTRICAL-Rough 12/23/2025 Approved ALEXANDER HANDY
Green Building Rough 12/23/2025 Not Ready for Inspection ALEXANDER HANDY
HVAC-Rough 12/23/2025 Approved ALEXANDER HANDY
PLUMBING-Rough 12/23/2025 Approved ALEXANDER HANDY
Sewer 12/23/2025 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 1/8/2026 Approved ALEXANDER HANDY
Green Building Rough 1/8/2026 Approved ALEXANDER HANDY
Insulation 1/8/2026 Conditional Approval ALEXANDER HANDY
Drywall Nailing 1/23/2026 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 1/23/2026 Partial Approval KRISTEN CAUSEY
Interior/Exterior Lathing 2/3/2026 Approved KRISTEN CAUSEY
Shower Pan 2/3/2026 Approved KRISTEN CAUSEY
ELECTRICAL-Final 4/29/2026 Approved ALEXANDER HANDY
Final 4/29/2026 Corrections Issued ALEXANDER HANDY
Green Building Final 4/29/2026 Not Ready for Inspection ALEXANDER HANDY
HVAC-Final 4/29/2026 Approved ALEXANDER HANDY
PLUMBING-Final 4/29/2026 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 4/29/2026 SGSOV Approved ALEXANDER HANDY
Smoke Detectors 4/29/2026 Approved ALEXANDER HANDY