7301-7303 N CASABA AVE 91306
Certificate Information: 7301-7303 N CASABA AVE 91306
- Application / Permit
- 25016-20000-25959
- Plan Check / Job No.
- B25VN24991
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER GC 66323(a)(1).
- Permit Issued
- Issued on 9/11/2025
- Issuing Office
- Valley
- Current Status
- Issued on 9/11/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/27/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/3/2025 | ISIS ARGUETA |
| Corrections Issued | 9/3/2025 | ISIS ARGUETA |
| Building Plans Picked Up | 9/4/2025 | APPLICANT |
| Plan Check Approved | 9/11/2025 | YAQUB MIRZA |
| Issued | 9/11/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/9/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 9/9/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 9/10/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/26/2025 | Partial Inspection | HENRY KIM |
| Excavation/Setback/Form/Re-Bar | 10/28/2025 | Approved | ALEXANDER HANDY |
| Footing/Foundation/Slab | 10/28/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 10/28/2025 | Partial Approval | ALEXANDER HANDY |
| Sewer | 10/28/2025 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 12/23/2025 | Corrections Issued | ALEXANDER HANDY |
| ELECTRICAL-Rough | 12/23/2025 | Approved | ALEXANDER HANDY |
| Green Building Rough | 12/23/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| HVAC-Rough | 12/23/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 12/23/2025 | Approved | ALEXANDER HANDY |
| Sewer | 12/23/2025 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 1/8/2026 | Approved | ALEXANDER HANDY |
| Green Building Rough | 1/8/2026 | Approved | ALEXANDER HANDY |
| Insulation | 1/8/2026 | Conditional Approval | ALEXANDER HANDY |
| Drywall Nailing | 1/23/2026 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 1/23/2026 | Partial Approval | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 2/3/2026 | Approved | KRISTEN CAUSEY |
| Shower Pan | 2/3/2026 | Approved | KRISTEN CAUSEY |
| ELECTRICAL-Final | 4/29/2026 | Approved | ALEXANDER HANDY |
| Final | 4/29/2026 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 4/29/2026 | Not Ready for Inspection | ALEXANDER HANDY |
| HVAC-Final | 4/29/2026 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 4/29/2026 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 4/29/2026 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 4/29/2026 | Approved | ALEXANDER HANDY |