13243-13245 W LEACH ST 91342

Certificate Information: 13243-13245 W LEACH ST 91342

Application / Permit
25016-20000-25922
Plan Check / Job No.
B25VN24938
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: CONVERT (E) ATTACHED 2-CAR GARAGE TO BE CONVERTED TO ADU PER GC 66323(A)(1)
Permit Issued
Issued on 10/25/2025
Issuing Office
Current Status
CofO Issued on 7/21/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/26/2025 APPLICANT
Assigned to Plan Check Engineer 8/29/2025 SUNMIN LEE
Corrections Issued 8/29/2025 SUNMIN LEE
Applicant returned to address corrections 10/20/2025 SUNMIN LEE
Plan Check Approved 10/24/2025 SUNMIN LEE
Issued 10/25/2025 APPLICANT
CofO in Progress 7/8/2026 KEVIN BERBERYAN
Permit Finaled 7/21/2026 DANIEL ORRANTE
CofO Issued 7/21/2026 DANIEL ORRANTE
Permit Finaled 7/21/2026 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 9/15/2025 MICHAEL BROWN
Sewer availability Cleared 9/15/2025 MICHAEL BROWN
Eng Process Fee Ord 176,300 Cleared 9/16/2025 MICHAEL BROWN
Grading Pre-Inspection Cleared 10/2/2025 ALEXANDER HELFER
Roof/Waste drainage to street Cleared 10/20/2025 MICHAEL BROWN

Contact Information

Contractor Owner-Builder       ,
Engineer Valdez,, Edgar Guadalupe; Lic. No.: E23558 1133 N SIESTA AVE      LA PUENTE, CA 91746

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/28/2025 Partial Inspection KEVIN BERBERYAN
Footing/Foundation/Slab 12/2/2025 Corrections Issued KEVIN BERBERYAN
PLUMBING-Rough 12/2/2025 Partial Approval KEVIN BERBERYAN
BUILDING-Rough-Frame 1/7/2026 Corrections Issued MICHEL ABAJAN
ELECTRICAL-Rough 1/7/2026 Approved MICHEL ABAJAN
Green Building Rough 1/7/2026 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Rough 1/7/2026 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 1/12/2026 Corrections Issued KEVIN BERBERYAN
Green Building Rough 1/12/2026 Not Ready for Inspection KEVIN BERBERYAN
BUILDING-Rough-Frame 1/30/2026 Approved KEVIN BERBERYAN
Green Building Rough 1/30/2026 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 1/30/2026 Approved KEVIN BERBERYAN
Gas Test 2/3/2026 Approved KEVIN BERBERYAN
Insulation 2/3/2026 Approved KEVIN BERBERYAN
Drywall Nailing 2/6/2026 Corrections Issued MICHAEL CORTEZ
Final 3/27/2026 Corrections Issued KEVIN BERBERYAN
Green Building Final 3/27/2026 Not Ready for Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 3/27/2026 SGSOV Approved KEVIN BERBERYAN
Smoke Detectors 3/27/2026 Not Ready for Inspection KEVIN BERBERYAN
Final 4/13/2026 Partial Approval KEVIN BERBERYAN
Green Building Final 4/13/2026 Approved KEVIN BERBERYAN
Smoke Detectors 4/13/2026 Approved KEVIN BERBERYAN
Final 7/8/2026 OK to Issue CofO KEVIN BERBERYAN