7541 N GLORIA AVE 91406

Certificate Information: 7541 N GLORIA AVE 91406

Application / Permit
25016-20000-25722
Plan Check / Job No.
B25VN24748
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN-- CONVERT EXISITNG DETACHED GARAGE INTO NEW ACCESSORY DWELLING UNIT PER GC 66323(a)(1) . ALL WORK PER WFPP
Permit Issued
Issued on 9/26/2025
Issuing Office
Current Status
CofO Issued on 3/17/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/27/2025 APPLICANT
Assigned to Plan Check Engineer 9/2/2025 ARAMIK SHAHMIRZAIAN
Corrections Issued 9/3/2025 ARAMIK SHAHMIRZAIAN
Applicant returned to address corrections 9/23/2025 ARAMIK SHAHMIRZAIAN
Plan Check Approved 9/25/2025 ARAMIK SHAHMIRZAIAN
Issued 9/26/2025 APPLICANT
CofO in Progress 2/9/2026 GAREN HAYRAPETYAN
CofO Issued 3/17/2026 RUBEN SALAS
Permit Finaled 3/17/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/8/2025 LEE GUILBEAUX
Sewer availability Cleared 9/8/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 9/8/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 9/10/2025 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/22/2025 Conditional Approval JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 10/27/2025 Approved JACK KARGODORIAN
Footing/Foundation/Slab 10/27/2025 Approved JACK KARGODORIAN
PLUMBING-Rough 10/27/2025 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 11/14/2025 Partial Approval GAREN HAYRAPETYAN
ELECTRICAL-Rough 11/14/2025 Conditional Approval GAREN HAYRAPETYAN
HVAC-Rough 11/14/2025 Corrections Issued GAREN HAYRAPETYAN
PLUMBING-Rough 11/14/2025 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 11/19/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Green Building Rough 11/19/2025 Approved GAREN HAYRAPETYAN
HVAC-Rough 11/19/2025 Approved GAREN HAYRAPETYAN
Insulation 11/19/2025 Conditional Approval GAREN HAYRAPETYAN
Interior/Exterior Lathing 11/19/2025 Partial Approval GAREN HAYRAPETYAN
BUILDING-Rough-Frame 11/24/2025 Approved GAREN HAYRAPETYAN
Drywall Nailing 11/26/2025 Approved LOUIS ESCOTO
Insulation 11/26/2025 Approved LOUIS ESCOTO
Shower Pan 11/26/2025 Corrections Issued LOUIS ESCOTO
Shower Pan 12/2/2025 Approved LOUIS ESCOTO
Interior/Exterior Lathing 12/8/2025 Approved LOUIS ESCOTO
Pre-Inspection 12/18/2025 Approved JACK KARGODORIAN
Final 2/5/2026 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 2/5/2026 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 2/5/2026 SGSOV Approved GAREN HAYRAPETYAN
Smoke Detectors 2/5/2026 Approved GAREN HAYRAPETYAN
Final 2/9/2026 OK to Issue CofO GAREN HAYRAPETYAN
Service/Power Release 2/9/2026 Approved GAREN HAYRAPETYAN
Sewer 2/9/2026 Approved GAREN HAYRAPETYAN