7541 N GLORIA AVE 91406
Certificate Information: 7541 N GLORIA AVE 91406
- Application / Permit
- 25016-20000-25722
- Plan Check / Job No.
- B25VN24748
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN-- CONVERT EXISITNG DETACHED GARAGE INTO NEW ACCESSORY DWELLING UNIT PER GC 66323(a)(1) . ALL WORK PER WFPP
- Permit Issued
- Issued on 9/26/2025
- Issuing Office
- Current Status
- CofO Issued on 3/17/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/27/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2025 | ARAMIK SHAHMIRZAIAN |
| Corrections Issued | 9/3/2025 | ARAMIK SHAHMIRZAIAN |
| Applicant returned to address corrections | 9/23/2025 | ARAMIK SHAHMIRZAIAN |
| Plan Check Approved | 9/25/2025 | ARAMIK SHAHMIRZAIAN |
| Issued | 9/26/2025 | APPLICANT |
| CofO in Progress | 2/9/2026 | GAREN HAYRAPETYAN |
| CofO Issued | 3/17/2026 | RUBEN SALAS |
| Permit Finaled | 3/17/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/8/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 9/8/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 9/8/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 9/10/2025 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/22/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 10/27/2025 | Approved | JACK KARGODORIAN |
| Footing/Foundation/Slab | 10/27/2025 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 10/27/2025 | Partial Approval | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 11/14/2025 | Partial Approval | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 11/14/2025 | Conditional Approval | GAREN HAYRAPETYAN |
| HVAC-Rough | 11/14/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 11/14/2025 | Approved | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 11/19/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Green Building Rough | 11/19/2025 | Approved | GAREN HAYRAPETYAN |
| HVAC-Rough | 11/19/2025 | Approved | GAREN HAYRAPETYAN |
| Insulation | 11/19/2025 | Conditional Approval | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 11/19/2025 | Partial Approval | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 11/24/2025 | Approved | GAREN HAYRAPETYAN |
| Drywall Nailing | 11/26/2025 | Approved | LOUIS ESCOTO |
| Insulation | 11/26/2025 | Approved | LOUIS ESCOTO |
| Shower Pan | 11/26/2025 | Corrections Issued | LOUIS ESCOTO |
| Shower Pan | 12/2/2025 | Approved | LOUIS ESCOTO |
| Interior/Exterior Lathing | 12/8/2025 | Approved | LOUIS ESCOTO |
| Pre-Inspection | 12/18/2025 | Approved | JACK KARGODORIAN |
| Final | 2/5/2026 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Final | 2/5/2026 | Approved | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 2/5/2026 | SGSOV Approved | GAREN HAYRAPETYAN |
| Smoke Detectors | 2/5/2026 | Approved | GAREN HAYRAPETYAN |
| Final | 2/9/2026 | OK to Issue CofO | GAREN HAYRAPETYAN |
| Service/Power Release | 2/9/2026 | Approved | GAREN HAYRAPETYAN |
| Sewer | 2/9/2026 | Approved | GAREN HAYRAPETYAN |