10029-10031 N NOBLE AVE 91345
Certificate Information: 10029-10031 N NOBLE AVE 91345
- Application / Permit
- 25016-20000-25620
- Plan Check / Job No.
- B25VN24646
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT EX ATTACHED GARAGE INTO JR ACCESSORY DWELLING UNIT PER GCS 66323(a)(1) & 66333. ALL WORK PER WFPP.
- Permit Issued
- Issued on 9/11/2025
- Issuing Office
- Current Status
- CofO Issued on 3/26/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/25/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2025 | HAYATO TSUCHIYA |
| Corrections Issued | 8/30/2025 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 9/2/2025 | APPLICANT |
| Issued | 9/11/2025 | APPLICANT |
| CofO in Progress | 3/2/2026 | JENNIFER RABUCHIN |
| CofO Issued | 3/26/2026 | RUBEN SALAS |
| Permit Finaled | 3/26/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/5/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 9/5/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 9/5/2025 | SAFA JAVANMARDI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/18/2025 | Partial Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 9/23/2025 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/8/2025 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/8/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 10/8/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 10/8/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Special/Order Compliance | 10/8/2025 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/14/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/14/2025 | Approved | JENNIFER RABUCHIN |
| Gas Test | 10/14/2025 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 10/14/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 10/14/2025 | Approved | JENNIFER RABUCHIN |
| Insulation | 10/14/2025 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 10/14/2025 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 10/14/2025 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 10/20/2025 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 10/20/2025 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 10/23/2025 | Approved | MICHAEL CORTEZ |
| Pre-Inspection | 10/29/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 2/23/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 2/23/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 2/23/2026 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 2/23/2026 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 2/23/2026 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 2/23/2026 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 2/23/2026 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 2/27/2026 | Approved | JENNIFER RABUCHIN |
| Final | 2/27/2026 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 2/27/2026 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 2/27/2026 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 2/27/2026 | SGSOV Approved | JENNIFER RABUCHIN |