10029-10031 N NOBLE AVE 91345

Certificate Information: 10029-10031 N NOBLE AVE 91345

Application / Permit
25016-20000-25620
Plan Check / Job No.
B25VN24646
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT EX ATTACHED GARAGE INTO JR ACCESSORY DWELLING UNIT PER GCS 66323(a)(1) & 66333. ALL WORK PER WFPP.
Permit Issued
Issued on 9/11/2025
Issuing Office
Current Status
CofO Issued on 3/26/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/25/2025 APPLICANT
Assigned to Plan Check Engineer 8/29/2025 HAYATO TSUCHIYA
Corrections Issued 8/30/2025 HAYATO TSUCHIYA
Building Plans Picked Up 9/2/2025 APPLICANT
Issued 9/11/2025 APPLICANT
CofO in Progress 3/2/2026 JENNIFER RABUCHIN
CofO Issued 3/26/2026 RUBEN SALAS
Permit Finaled 3/26/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/5/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 9/5/2025 SAFA JAVANMARDI
Sewer availability Cleared 9/5/2025 SAFA JAVANMARDI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/18/2025 Partial Approval RAUL OLAGI
Footing/Foundation/Slab 9/23/2025 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 10/8/2025 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 10/8/2025 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 10/8/2025 Approved JENNIFER RABUCHIN
HVAC-Rough 10/8/2025 Approved JENNIFER RABUCHIN
PLUMBING-Rough 10/8/2025 Corrections Issued JENNIFER RABUCHIN
Special/Order Compliance 10/8/2025 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 10/14/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 10/14/2025 Approved JENNIFER RABUCHIN
Gas Test 10/14/2025 Partial Approval JENNIFER RABUCHIN
Green Building Rough 10/14/2025 Approved JENNIFER RABUCHIN
HVAC-Rough 10/14/2025 Approved JENNIFER RABUCHIN
Insulation 10/14/2025 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 10/14/2025 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 10/14/2025 Approved JENNIFER RABUCHIN
Drywall Nailing 10/20/2025 Approved JENNIFER RABUCHIN
Shower Pan 10/20/2025 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 10/23/2025 Approved MICHAEL CORTEZ
Pre-Inspection 10/29/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 2/23/2026 Corrections Issued JENNIFER RABUCHIN
Final 2/23/2026 Corrections Issued JENNIFER RABUCHIN
Green Building Final 2/23/2026 Approved JENNIFER RABUCHIN
HVAC-Final 2/23/2026 Approved JENNIFER RABUCHIN
PLUMBING-Final 2/23/2026 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 2/23/2026 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 2/23/2026 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 2/27/2026 Approved JENNIFER RABUCHIN
Final 2/27/2026 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 2/27/2026 Approved JENNIFER RABUCHIN
PLUMBING-Final 2/27/2026 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 2/27/2026 SGSOV Approved JENNIFER RABUCHIN