16653 W JERSEY ST 91344

Certificate Information: 16653 W JERSEY ST 91344

Application / Permit
25016-20000-25431
Plan Check / Job No.
B25VN24419
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: Convert existing detached garage to new ADU Per State Law and GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 10/7/2025
Issuing Office
Current Status
CofO Issued on 3/3/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/21/2025 APPLICANT
Assigned to Plan Check Engineer 8/26/2025 ZAW HAN
Corrections Issued 8/27/2025 ZAW HAN
Applicant returned to address corrections 9/24/2025 ZAW HAN
Plan Check Approved 9/30/2025 ZAW HAN
Issued 10/7/2025 APPLICANT
CofO in Progress 2/20/2026 CHRISTOPHER ROJAS
Permit Finaled 3/3/2026 RUBEN SALAS
CofO Issued 3/3/2026 RUBEN SALAS
Permit Finaled 3/3/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/3/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 9/3/2025 SAFA JAVANMARDI
Sewer availability Cleared 9/3/2025 SAFA JAVANMARDI
Construction near power lines Cleared 9/18/2025 GEVORK KARAPETYAN
Construction within easement Cleared 9/18/2025 GEVORK KARAPETYAN
Eng Process Fee Ord 176,300 Cleared 9/22/2025 SAFA JAVANMARDI

Contact Information

Contractor New Beginning Construction Company Corp The; Lic. No.: 848904-B       ,
Contractor New Beginnning Construction Company The; Lic. No.: 848904-B       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/21/2025 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 11/17/2025 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 11/17/2025 Partial Approval CHRISTOPHER ROJAS
Underground Mechanical 11/17/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Underground Mechanical 11/19/2025 Partial Approval CHRISTOPHER ROJAS
ELECTRICAL-Rough 12/4/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 12/4/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 12/4/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 12/8/2025 Corrections Issued KEVIN BERBERYAN
HVAC-Rough 12/8/2025 Approved CHRISTOPHER ROJAS
HVAC-Rough 12/8/2025 Approved KEVIN BERBERYAN
PLUMBING-Rough 12/8/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Wood Frame 12/8/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Insulation 12/10/2025 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 12/10/2025 Partial Approval KEVIN BERBERYAN
BUILDING-Rough-Frame 12/11/2025 Approved KEVIN BERBERYAN
Shower Pan 12/11/2025 Approved KEVIN BERBERYAN
Drywall Nailing 12/17/2025 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 12/17/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 2/3/2026 Corrections Issued CHRISTOPHER ROJAS
Final 2/3/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Final 2/3/2026 Approved CHRISTOPHER ROJAS
HVAC-Final 2/3/2026 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Final 2/3/2026 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 2/3/2026 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 2/3/2026 Approved CHRISTOPHER ROJAS
Final 2/18/2026 OK to Issue CofO CHRISTOPHER ROJAS