17423 W LULL ST 91325

Certificate Information: 17423 W LULL ST 91325

Application / Permit
25016-20000-25120
Plan Check / Job No.
B25VN24066
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: CONVERT (E) GARAGE AND STORAGE TO ACCESSORY DWELLING UNIT PER GC 66323(a)(1).
Permit Issued
Issued on 11/17/2025
Issuing Office
Current Status
Issued on 11/17/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/20/2025 APPLICANT
Assigned to Plan Check Engineer 8/22/2025 ISIS ARGUETA
Corrections Issued 8/25/2025 ISIS ARGUETA
Applicant returned to address corrections 10/8/2025 ISIS ARGUETA
Plan Check Approved 11/17/2025 ISIS ARGUETA
Issued 11/17/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/6/2025 COLIN LOREDO
Sewer availability Cleared 9/6/2025 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 9/8/2025 COLIN LOREDO
Construction near power lines Cleared 10/2/2025 ENRIQUE ACOSTA
Construction within easement Cleared 10/2/2025 ENRIQUE ACOSTA

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/29/2026 Conditional Approval JOAQUIN GREENOUGH
BUILDING-Rough-Frame 3/3/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 3/3/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 3/3/2026 Conditional Approval ROBERTO PALACIOS-LOPEZ
Sewer 3/3/2026 Approved ROBERTO PALACIOS-LOPEZ
Underground Mechanical 3/3/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 3/9/2026 Partial Approval KIRK SANDERS
Footing/Foundation/Slab 3/9/2026 Approved KIRK SANDERS
HVAC-Rough 3/9/2026 Approved KIRK SANDERS
PLUMBING-Rough 3/9/2026 Approved KIRK SANDERS
Underground Mechanical 3/9/2026 Partial Approval KIRK SANDERS
BUILDING-Rough-Frame 3/13/2026 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 3/13/2026 Approved JAVIER RAMOS JR
Green Building Rough 3/13/2026 Approved JAVIER RAMOS JR
Insulation 3/17/2026 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 3/17/2026 Partial Approval ROBERTO PALACIOS-LOPEZ
Shower Pan 3/17/2026 Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 3/17/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Drywall Nailing 3/25/2026 Approved JOSE AVILA
ELECTRICAL-Rough 3/27/2026 Approved KEVIN BERBERYAN
Underground Mechanical 3/27/2026 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 4/9/2026 Partial Approval DAVID MATSON
Final 6/3/2026 Corrections Issued MICHAEL CORTEZ
Green Building Final 6/3/2026 Corrections Issued MICHAEL CORTEZ
SGSOV-Seismic Gas S/O Valve 6/3/2026 SGSOV Approved MICHAEL CORTEZ
Smoke Detectors 6/3/2026 Approved MICHAEL CORTEZ