17423 W LULL ST 91325
Certificate Information: 17423 W LULL ST 91325
- Application / Permit
- 25016-20000-25120
- Plan Check / Job No.
- B25VN24066
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: CONVERT (E) GARAGE AND STORAGE TO ACCESSORY DWELLING UNIT PER GC 66323(a)(1).
- Permit Issued
- Issued on 11/17/2025
- Issuing Office
- Current Status
- Issued on 11/17/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/20/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/22/2025 | ISIS ARGUETA |
| Corrections Issued | 8/25/2025 | ISIS ARGUETA |
| Applicant returned to address corrections | 10/8/2025 | ISIS ARGUETA |
| Plan Check Approved | 11/17/2025 | ISIS ARGUETA |
| Issued | 11/17/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/6/2025 | COLIN LOREDO |
| Sewer availability | Cleared | 9/6/2025 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 9/8/2025 | COLIN LOREDO |
| Construction near power lines | Cleared | 10/2/2025 | ENRIQUE ACOSTA |
| Construction within easement | Cleared | 10/2/2025 | ENRIQUE ACOSTA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yenjai,, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/29/2026 | Conditional Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 3/3/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 3/3/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 3/3/2026 | Conditional Approval | ROBERTO PALACIOS-LOPEZ |
| Sewer | 3/3/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 3/3/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 3/9/2026 | Partial Approval | KIRK SANDERS |
| Footing/Foundation/Slab | 3/9/2026 | Approved | KIRK SANDERS |
| HVAC-Rough | 3/9/2026 | Approved | KIRK SANDERS |
| PLUMBING-Rough | 3/9/2026 | Approved | KIRK SANDERS |
| Underground Mechanical | 3/9/2026 | Partial Approval | KIRK SANDERS |
| BUILDING-Rough-Frame | 3/13/2026 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 3/13/2026 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 3/13/2026 | Approved | JAVIER RAMOS JR |
| Insulation | 3/17/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 3/17/2026 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 3/17/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 3/17/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 3/25/2026 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 3/27/2026 | Approved | KEVIN BERBERYAN |
| Underground Mechanical | 3/27/2026 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 4/9/2026 | Partial Approval | DAVID MATSON |
| Final | 6/3/2026 | Corrections Issued | MICHAEL CORTEZ |
| Green Building Final | 6/3/2026 | Corrections Issued | MICHAEL CORTEZ |
| SGSOV-Seismic Gas S/O Valve | 6/3/2026 | SGSOV Approved | MICHAEL CORTEZ |
| Smoke Detectors | 6/3/2026 | Approved | MICHAEL CORTEZ |