16140 W VALERIO ST Suite#A 91406

Certificate Information: 16140 W VALERIO ST Suite#A 91406

Application / Permit
25016-20000-25026
Plan Check / Job No.
B25VN23939
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
ePlan: Tenant Improvement w/ interior and exterior improvements. Repave and re-stripe existing parking area including accessible parking and signage.
Permit Issued
Issued on 12/10/2025
Issuing Office
Current Status
CofO Issued on 5/1/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/19/2025 APPLICANT
Assigned to Zoning Architect 8/21/2025 RONALD GREENE
Assigned to Plan Check Engineer 8/28/2025 HERNAN ARREOLA
Corrections Issued 9/10/2025 HERNAN ARREOLA
Quality Review Completed 9/26/2025 GARO TELMI
Plan Check Approved 12/5/2025 HERNAN ARREOLA
Issued 12/10/2025 APPLICANT
Permit Finaled 5/1/2026 JEFFREY DURAN
Permit Finaled 5/1/2026 JEFFREY DURAN
CofO Issued 5/1/2026 JEFFREY DURAN

Permit Application Clearance Information

Zoning Plan Check Cleared 10/30/2025 Ronald Greene
Green Code Cleared 11/6/2025 MICHAEL AYERS
DAS Clearance Cleared 11/20/2025 Ricardo Ramirez Solis

Contact Information

Architect Villarruel,, Antonio; Lic. No.: NA25143       ,
Contractor Intertex General Contractors Inc; Lic. No.: 482946-B       ,
Contractor Intertex Inc; Lic. No.: 482946-B       ,
Engineer Martinez,, Jose Luis; Lic. No.: C68931 5806 COLDWATER CYN APT 4      NORTH HOLLYWOOD, CA 91607
Engineer Martinez,, Jose Luis; Lic. No.: NA68931       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/7/2026 Partial Inspection DEANDRE HOFFMAN
Footing/Foundation/Slab 1/29/2026 Approved EDWIN GREGORYONA
Light Gage Steel Frame 2/3/2026 Partial Approval EDWIN GREGORYONA
Drywall Nailing 2/6/2026 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 2/6/2026 Approved EDWIN GREGORYONA
Drywall Nailing 3/3/2026 Approved EDWIN GREGORYONA
Special/Order Compliance 3/6/2026 Approved EDWIN GREGORYONA
T-Bar Ceiling 3/17/2026 Approved EDWIN GREGORYONA
Final 4/7/2026 Not Ready for Inspection EDWIN GREGORYONA
Green Building Final 4/7/2026 Approved EDWIN GREGORYONA
Green Building Rough 4/7/2026 Approved EDWIN GREGORYONA
Reinforced Masonry Frame 4/7/2026 Approved EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 4/7/2026 SGSOV Not Ready EDWIN GREGORYONA
Smoke Detectors 4/7/2026 Approved EDWIN GREGORYONA
Final 4/16/2026 Partial Inspection EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 4/16/2026 SGSOV Approved EDWIN GREGORYONA
Final 4/21/2026 Partial Inspection DEANDRE HOFFMAN
Final 4/27/2026 Conditional Approval EDWIN GREGORYONA