13895-13897 N WALLABI AVE 91342

Certificate Information: 13895-13897 N WALLABI AVE 91342

Application / Permit
25016-20000-25021
Plan Check / Job No.
B25VN23930
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. CONVERSION OF ATTACHED GARAGE INTO A.D.U. PER GCS 66323(a)(1).
Permit Issued
Issued on 9/10/2025
Issuing Office
Current Status
Issued on 9/10/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/18/2025 APPLICANT
Assigned to Plan Check Engineer 8/20/2025 LAWRENCE QUIRANTE
Corrections Issued 8/20/2025 LAWRENCE QUIRANTE
Applicant returned to address corrections 8/28/2025 SUNMIN LEE
Applicant returned to address corrections 9/10/2025 LAWRENCE QUIRANTE
Plan Check Approved 9/10/2025 FERNANDO FLORES
No Progress 9/10/2025 FERNANDO FLORES
Plan Check Approved 9/10/2025 FERNANDO FLORES
Issued 9/10/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/8/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 9/8/2025 SAFA JAVANMARDI
Sewer availability Cleared 9/8/2025 SAFA JAVANMARDI

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: NA76761       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/24/2025 Partial Inspection KEVIN BERBERYAN
BUILDING-Rough-Frame 10/14/2025 Partial Approval KEVIN BERBERYAN
Footing/Foundation/Slab 10/14/2025 Corrections Issued KEVIN BERBERYAN
Green Building Rough 10/14/2025 Not Ready for Inspection KEVIN BERBERYAN
BUILDING-Rough-Frame 10/20/2025 Corrections Issued KEVIN BERBERYAN
ELECTRICAL-Rough 10/20/2025 Approved KEVIN BERBERYAN
PLUMBING-Rough 10/20/2025 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 10/28/2025 Approved KEVIN BERBERYAN
HVAC-Rough 10/28/2025 Not Ready for Inspection KEVIN BERBERYAN
Interior/Exterior Lathing 10/28/2025 Approved KEVIN BERBERYAN
PLUMBING-Rough 10/28/2025 Approved KEVIN BERBERYAN
HVAC-Rough 11/5/2025 Approved KEVIN BERBERYAN
Insulation 11/5/2025 Approved KEVIN BERBERYAN
Shower Pan 11/5/2025 Approved KEVIN BERBERYAN
Drywall Nailing 11/7/2025 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 11/7/2025 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 1/15/2026 Approved KEVIN BERBERYAN
Final 1/15/2026 Corrections Issued KEVIN BERBERYAN
Green Building Final 1/15/2026 Not Ready for Inspection KEVIN BERBERYAN
Green Building Rough 1/15/2026 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 1/15/2026 SGSOV Approved KEVIN BERBERYAN
Smoke Detectors 1/15/2026 Approved KEVIN BERBERYAN