5105 N TENDILLA AVE 91364

Certificate Information: 5105 N TENDILLA AVE 91364

Application / Permit
25016-20000-24890
Plan Check / Job No.
B25VN23783
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL TO EX. SFD AT KITCHEN AND REMOVAL OF LOAD BEARING WALL.
Permit Issued
Issued on 8/19/2025
Issuing Office
Valley
Current Status
Permit Finaled on 2/25/2026

Permit Application Status History

Submitted 8/15/2025 APPLICANT
Assigned to Plan Check Engineer 8/15/2025 ROSENDO MEDINA
Corrections Issued 8/15/2025 ROSENDO MEDINA
Plan Check Approved 8/19/2025 SEWADA ZADOORAN MILAGARDI
Issued 8/19/2025 APPLICANT
Permit Finaled 2/25/2026 JOHN HAYES

Permit Application Clearance Information

Grading Pre-Inspection Cleared 8/19/2025 ALEXANDER HELFER

Contact Information

Contractor Owner-Builder       ,
Engineer Taroian,, Armen; Lic. No.: C78011 411 PALM DR APT 204      GLENDALE, CA 91202

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/16/2025 Corrections Issued JOHN HAYES
Deputy Drilled-In Anchors 9/17/2025 Partial Approval SEAN WIRCH
ELECTRICAL-Rough 9/18/2025 Not Ready for Inspection JOHN HAYES
Excavation/Setback/Form/Re-Bar 9/18/2025 Partial Approval JOHN HAYES
HVAC-Rough 9/18/2025 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 9/18/2025 Not Ready for Inspection JOHN HAYES
Deputy Reinf. Concrete 9/22/2025 Partial Approval SEAN WIRCH
BUILDING-Rough-Frame 10/2/2025 Corrections Issued JOHN HAYES
PLUMBING-Rough 10/2/2025 Not Ready for Inspection JOHN HAYES
Rough-Elec/Plmb/HVAC 10/2/2025 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 10/29/2025 No Access for Inspection JOHN HAYES
Rough-Elec/Plmb/HVAC 10/29/2025 No Access for Inspection JOHN HAYES
BUILDING-Rough-Frame 10/31/2025 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 10/31/2025 Not Ready for Inspection JOHN HAYES
HVAC-Rough 10/31/2025 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 10/31/2025 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 11/6/2025 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 11/6/2025 Not Ready for Inspection JOHN HAYES
HVAC-Rough 11/6/2025 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 11/6/2025 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 11/25/2025 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 12/1/2025 Approved JEFFREY PARD
ELECTRICAL-Rough 12/1/2025 Approved JEFFREY PARD
HVAC-Rough 12/1/2025 Approved JEFFREY PARD
Interior/Exterior Lathing 12/1/2025 Approved JEFFREY PARD
PLUMBING-Rough 12/1/2025 Approved JEFFREY PARD
Insulation 12/3/2025 Not Ready for Inspection JOHN HAYES
Insulation 12/4/2025 Approved SEAN WIRCH
Interior/Exterior Lathing 12/4/2025 Approved SEAN WIRCH
Drywall Nailing 12/12/2025 Approved JON MCHUGH
Final 2/20/2026 Corrections Issued JOHN HAYES
SGSOV-Seismic Gas S/O Valve 2/20/2026 SGSOV Not Ready JOHN HAYES
Smoke Detectors 2/20/2026 Approved JOHN HAYES
Final 2/25/2026 Permit Finaled JOHN HAYES
SGSOV-Seismic Gas S/O Valve 2/25/2026 SGSOV Approved JOHN HAYES