5105 N TENDILLA AVE 91364
Certificate Information: 5105 N TENDILLA AVE 91364
- Application / Permit
- 25016-20000-24890
- Plan Check / Job No.
- B25VN23783
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO EX. SFD AT KITCHEN AND REMOVAL OF LOAD BEARING WALL.
- Permit Issued
- Issued on 8/19/2025
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 2/25/2026
Permit Application Status History
| Submitted | 8/15/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/15/2025 | ROSENDO MEDINA |
| Corrections Issued | 8/15/2025 | ROSENDO MEDINA |
| Plan Check Approved | 8/19/2025 | SEWADA ZADOORAN MILAGARDI |
| Issued | 8/19/2025 | APPLICANT |
| Permit Finaled | 2/25/2026 | JOHN HAYES |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 8/19/2025 | ALEXANDER HELFER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Taroian,, Armen; Lic. No.: C78011 | 411 PALM DR APT 204 GLENDALE, CA 91202 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/16/2025 | Corrections Issued | JOHN HAYES |
| Deputy Drilled-In Anchors | 9/17/2025 | Partial Approval | SEAN WIRCH |
| ELECTRICAL-Rough | 9/18/2025 | Not Ready for Inspection | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 9/18/2025 | Partial Approval | JOHN HAYES |
| HVAC-Rough | 9/18/2025 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 9/18/2025 | Not Ready for Inspection | JOHN HAYES |
| Deputy Reinf. Concrete | 9/22/2025 | Partial Approval | SEAN WIRCH |
| BUILDING-Rough-Frame | 10/2/2025 | Corrections Issued | JOHN HAYES |
| PLUMBING-Rough | 10/2/2025 | Not Ready for Inspection | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 10/2/2025 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 10/29/2025 | No Access for Inspection | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 10/29/2025 | No Access for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 10/31/2025 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 10/31/2025 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 10/31/2025 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 10/31/2025 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 11/6/2025 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 11/6/2025 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 11/6/2025 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 11/6/2025 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 11/25/2025 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 12/1/2025 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 12/1/2025 | Approved | JEFFREY PARD |
| HVAC-Rough | 12/1/2025 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 12/1/2025 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 12/1/2025 | Approved | JEFFREY PARD |
| Insulation | 12/3/2025 | Not Ready for Inspection | JOHN HAYES |
| Insulation | 12/4/2025 | Approved | SEAN WIRCH |
| Interior/Exterior Lathing | 12/4/2025 | Approved | SEAN WIRCH |
| Drywall Nailing | 12/12/2025 | Approved | JON MCHUGH |
| Final | 2/20/2026 | Corrections Issued | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 2/20/2026 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 2/20/2026 | Approved | JOHN HAYES |
| Final | 2/25/2026 | Permit Finaled | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 2/25/2026 | SGSOV Approved | JOHN HAYES |