10399-10401 N RUBIO AVE 91344
Certificate Information: 10399-10401 N RUBIO AVE 91344
- Application / Permit
- 25016-20000-24807
- Plan Check / Job No.
- B25VN23699
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT (367 SQ FT) PER GCS 65852.2(e)(1)(A) and 65852.22
- Permit Issued
- Issued on 4/7/2026
- Issuing Office
- Valley
- Current Status
- CofO in Progress on 7/22/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/15/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/21/2025 | JEROME MAGAT PALMA |
| Corrections Issued | 8/23/2025 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 8/25/2025 | APPLICANT |
| Plan Check Approved | 9/29/2025 | MOHAMMAD ESMAILI |
| Issued | 4/7/2026 | APPLICANT |
| CofO in Progress | 7/22/2026 | JAVIER RAMOS JR |
Permit Application Clearance Information
| Address approval | Cleared | 9/25/2025 | KIMBERLY HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/26/2025 | CINDY QI |
| Sewer availability | Cleared | 9/26/2025 | CINDY QI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/10/2026 | Approved | CHRISTOPHER ROJAS |
| Special/Order Compliance | 4/10/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 4/15/2026 | Partial Approval | RAUL OLAGI |
| Deputy Drilled-In Anchors | 4/24/2026 | Conditional Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 4/24/2026 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Underground Mechanical | 4/24/2026 | Partial Approval | NICHOLAS TROWBRIDGE |
| Deputy Drilled-In Anchors | 4/29/2026 | Conditional Approval | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 5/1/2026 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 5/15/2026 | Partial Approval | KEVIN BERBERYAN |
| Rough-Elec/Plmb/HVAC | 5/15/2026 | Approved | KEVIN BERBERYAN |
| Sewer | 5/15/2026 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 5/22/2026 | Partial Approval | CHRISTOPHER ROJAS |
| Shower Pan | 5/22/2026 | Approved | CHRISTOPHER ROJAS |
| Insulation | 5/29/2026 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 6/2/2026 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 6/2/2026 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 6/2/2026 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 6/9/2026 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 7/10/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 7/10/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 7/10/2026 | Approved | CHRISTOPHER ROJAS |
| HVAC-Final | 7/10/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Final | 7/10/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 7/10/2026 | SGSOV Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 7/10/2026 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 7/21/2026 | Approved | JAVIER RAMOS JR |
| Final | 7/21/2026 | OK to Issue CofO | JAVIER RAMOS JR |
| HVAC-Final | 7/21/2026 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 7/21/2026 | Approved | JAVIER RAMOS JR |
| Service/Power Release | 7/21/2026 | Approved | JAVIER RAMOS JR |