10399-10401 N RUBIO AVE 91344

Certificate Information: 10399-10401 N RUBIO AVE 91344

Application / Permit
25016-20000-24807
Plan Check / Job No.
B25VN23699
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT (367 SQ FT) PER GCS 65852.2(e)(1)(A) and 65852.22
Permit Issued
Issued on 4/7/2026
Issuing Office
Valley
Current Status
CofO in Progress on 7/22/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/15/2025 APPLICANT
Assigned to Plan Check Engineer 8/21/2025 JEROME MAGAT PALMA
Corrections Issued 8/23/2025 JEROME MAGAT PALMA
Building Plans Picked Up 8/25/2025 APPLICANT
Plan Check Approved 9/29/2025 MOHAMMAD ESMAILI
Issued 4/7/2026 APPLICANT
CofO in Progress 7/22/2026 JAVIER RAMOS JR

Permit Application Clearance Information

Address approval Cleared 9/25/2025 KIMBERLY HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 9/26/2025 CINDY QI
Sewer availability Cleared 9/26/2025 CINDY QI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/10/2026 Approved CHRISTOPHER ROJAS
Special/Order Compliance 4/10/2026 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 4/15/2026 Partial Approval RAUL OLAGI
Deputy Drilled-In Anchors 4/24/2026 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 4/24/2026 Corrections Issued NICHOLAS TROWBRIDGE
Underground Mechanical 4/24/2026 Partial Approval NICHOLAS TROWBRIDGE
Deputy Drilled-In Anchors 4/29/2026 Conditional Approval CHRISTOPHER ROJAS
Footing/Foundation/Slab 5/1/2026 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 5/15/2026 Partial Approval KEVIN BERBERYAN
Rough-Elec/Plmb/HVAC 5/15/2026 Approved KEVIN BERBERYAN
Sewer 5/15/2026 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 5/22/2026 Partial Approval CHRISTOPHER ROJAS
Shower Pan 5/22/2026 Approved CHRISTOPHER ROJAS
Insulation 5/29/2026 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 6/2/2026 Approved KEVIN BERBERYAN
Green Building Rough 6/2/2026 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 6/2/2026 Approved KEVIN BERBERYAN
Drywall Nailing 6/9/2026 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 7/10/2026 Corrections Issued CHRISTOPHER ROJAS
Final 7/10/2026 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 7/10/2026 Approved CHRISTOPHER ROJAS
HVAC-Final 7/10/2026 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Final 7/10/2026 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 7/10/2026 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 7/10/2026 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 7/21/2026 Approved JAVIER RAMOS JR
Final 7/21/2026 OK to Issue CofO JAVIER RAMOS JR
HVAC-Final 7/21/2026 Approved JAVIER RAMOS JR
PLUMBING-Final 7/21/2026 Approved JAVIER RAMOS JR
Service/Power Release 7/21/2026 Approved JAVIER RAMOS JR