17324 W TULSA ST 91344
Certificate Information: 17324 W TULSA ST 91344
- Application / Permit
- 25016-20000-24484
- Plan Check / Job No.
- B25VN23313
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: CONVERT (E) DETACHED GARAGE INTO A 2ND DWELLING UNIT PER SB9 TWO-UNIT DEVELOPMENT PER WFPP. NFPA-13D FIRE SPRINKLER THRU-OUT
- Permit Issued
- Issued on 10/27/2025
- Issuing Office
- Current Status
- CofO Issued on 3/12/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/12/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/21/2025 | ALFRED RAMIREZ |
| Corrections Issued | 8/27/2025 | ALFRED RAMIREZ |
| Quality Review Completed | 9/4/2025 | STEVEN KIM |
| Plan Check Approved | 10/27/2025 | ALFRED RAMIREZ |
| Issued | 10/27/2025 | APPLICANT |
| CofO in Progress | 3/12/2026 | DAVID SCANTLIN |
| Permit Finaled | 3/12/2026 | JOHN JANSON |
| CofO Issued | 3/12/2026 | JOHN JANSON |
| Permit Finaled | 3/12/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/24/2025 | TONY CHIANG |
| Eng Process Fee Ord 176,300 | Cleared | 9/25/2025 | TONY CHIANG |
| Sewer availability | Cleared | 9/25/2025 | TONY CHIANG |
| Roof/Waste drainage to street | Cleared | 10/7/2025 | TONY CHIANG |
| Miscellaneous | Cleared | 10/16/2025 | MIGUEL CRISOSTOMO |
| Senate Bill 9 | Cleared | 10/21/2025 | FIPE LEILUA |
| ZI | Cleared | 10/21/2025 | FIPE LEILUA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/31/2025 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 11/4/2025 | Partial Approval | DAVID SCANTLIN |
| Sewer | 11/4/2025 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Rough | 12/2/2025 | Approved | STEVEN BACK |
| PLUMBING-Rough | 12/2/2025 | Approved | STEVEN BACK |
| Special/Order Compliance | 12/2/2025 | Corrections Issued | STEVEN BACK |
| BUILDING-Rough-Frame | 12/8/2025 | Corrections Issued | STEVEN BACK |
| HVAC-Rough | 12/8/2025 | Approved | STEVEN BACK |
| PLUMBING-Rough | 12/8/2025 | Approved | STEVEN BACK |
| Shower Pan | 12/8/2025 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 12/9/2025 | Partial Approval | STEVEN BACK |
| BUILDING-Rough-Frame | 12/12/2025 | Not Ready for Inspection | STEVEN BACK |
| Green Building Rough | 12/12/2025 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 12/12/2025 | Approved | STEVEN BACK |
| Verify Sprinkler Sign Off | 12/12/2025 | Approved | STEVEN BACK |
| Drywall Nailing | 12/16/2025 | Not Ready for Inspection | STEVEN BACK |
| BUILDING-Rough-Frame | 12/30/2025 | Approved | STEVEN BACK |
| Insulation | 12/30/2025 | Approved | STEVEN BACK |
| Drywall Nailing | 1/6/2026 | Approved | GEVORK IPCHYAN |
| Gas Test | 2/20/2026 | Approved | HENRY KIM |
| Underground Mechanical | 2/20/2026 | Approved | HENRY KIM |
| Final | 2/24/2026 | Corrections Issued | STEVEN BACK |
| Green Building Final | 2/24/2026 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 2/24/2026 | SGSOV Not Ready | STEVEN BACK |
| Smoke Detectors | 2/24/2026 | Approved | STEVEN BACK |
| Final | 3/6/2026 | Corrections Issued | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 3/6/2026 | SGSOV Approved | STEVEN BACK |
| Final | 3/11/2026 | OK to Issue CofO | DAVID SCANTLIN |
| Service/Power Release | 3/11/2026 | Approved | DAVID SCANTLIN |