3000-3002 S BEACH AVE 90291

Certificate Information: 3000-3002 S BEACH AVE 90291

Application / Permit
25016-20000-24314
Plan Check / Job No.
B25VN23114
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL (E) SFD, CONVERT (E) ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT PER GCS 66323(a)(1) and 66333 WITH RAISED FLOOR AND FLAT ROOF
Permit Issued
Issued on 1/8/2026
Issuing Office
Current Status
Issued on 1/8/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/11/2025 APPLICANT
Assigned to Plan Check Engineer 8/18/2025 ARTIN ZARUKIAN
Corrections Issued 8/18/2025 ARTIN ZARUKIAN
Building Plans Picked Up 8/20/2025 APPLICANT
Applicant returned to address corrections 12/18/2025 GIOVANNY CHAVEZ
Plan Check Approved 1/8/2026 ALEC MOUSAKHANIAN
Issued 1/8/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/26/2025 CINDY QI
Eng Process Fee Ord 176,300 Cleared 8/26/2025 CINDY QI
Sewer availability Cleared 8/26/2025 CINDY QI
Specific Plan Cleared 8/27/2025 RICHARD WOO
Specific Plan Cleared 8/27/2025 RICHARD WOO
Flood clearance Cleared 10/30/2025 TUYEN LE
Coastal Zone Cleared 1/6/2026 DALIA MOKAYED

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 1/9/2026 Approved RUBEN RIVAS
Deputy Drilled-In Anchors 1/21/2026 Approved RUBEN RIVAS
Footing/Foundation/Slab 1/21/2026 Approved RUBEN RIVAS
PLUMBING-Rough 1/29/2026 Partial Approval RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 2/3/2026 Partial Approval RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 2/12/2026 Partial Approval RUBEN RIVAS
Shower Pan 2/19/2026 Approved RUBEN RIVAS
BUILDING-Rough-Frame 2/26/2026 Partial Approval RUBEN RIVAS
ELECTRICAL-Rough 2/26/2026 Corrections Issued RUBEN RIVAS
Green Building Rough 2/26/2026 Not Ready for Inspection RUBEN RIVAS
HVAC-Rough 2/26/2026 Approved RUBEN RIVAS
ELECTRICAL-Rough 3/25/2026 Approved RUBEN RIVAS
Interior/Exterior Lathing 4/15/2026 Approved RUBEN RIVAS
Insulation 4/17/2026 Corrections Issued MICHAEL ALLEN
Interior/Exterior Lathing 4/21/2026 Approved RUBEN RIVAS
Drywall Nailing 4/23/2026 Approved RUBEN RIVAS
Green Building Rough 4/23/2026 Approved RUBEN RIVAS
ELECTRICAL-Final 6/1/2026 Approved RUBEN RIVAS
BUILDING-Rough-Frame 6/2/2026 Approved RUBEN RIVAS
Final 6/2/2026 Not Ready for Inspection RUBEN RIVAS
Green Building Final 6/2/2026 Not Ready for Inspection RUBEN RIVAS
SGSOV-Seismic Gas S/O Valve 6/2/2026 SGSOV Not Ready RUBEN RIVAS
Smoke Detectors 6/2/2026 Not Ready for Inspection RUBEN RIVAS