16900 W TULSA ST 91344

Certificate Information: 16900 W TULSA ST 91344

Application / Permit
25016-20000-24231
Plan Check / Job No.
B25VN23030
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ENCLOSE THE (E) OPEN PORCH, TO USE AS HABITABLE SAPCE TO THE (E) SFD AND ADD NEW SKYLIGHTS.ALL WORK PER WFPP
Permit Issued
Issued on 9/5/2025
Issuing Office
Valley
Current Status
CofO Issued on 1/10/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/8/2025 APPLICANT
Assigned to Plan Check Engineer 8/20/2025 NAREG ATARIAN
Corrections Issued 8/20/2025 NAREG ATARIAN
Applicant returned to address corrections 8/29/2025 KAMYAR EMAMI
Plan Check Approved 9/4/2025 NAREG ATARIAN
Issued 9/5/2025 APPLICANT
CofO in Progress 1/9/2026 CHRISTOPHER ROJAS
Permit Finaled 1/10/2026 RUBEN SALAS
CofO Issued 1/10/2026 RUBEN SALAS
Permit Finaled 1/10/2026 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/13/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 8/27/2025 DERRICK MAGEE

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/16/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Pre-Inspection 9/16/2025 Partial Approval CHRISTOPHER ROJAS
Footing/Foundation/Slab 10/10/2025 Partial Approval CHRISTOPHER ROJAS
Footing/Foundation/Slab 10/22/2025 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 11/4/2025 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 11/4/2025 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 11/4/2025 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 11/6/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
ELECTRICAL-Rough 11/6/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Green Building Rough 11/6/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
HVAC-Rough 11/6/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 11/25/2025 Partial Approval CHRISTOPHER ROJAS
ELECTRICAL-Rough 11/25/2025 Approved CHRISTOPHER ROJAS
Green Building Rough 11/25/2025 Approved CHRISTOPHER ROJAS
HVAC-Rough 11/25/2025 Approved CHRISTOPHER ROJAS
Insulation 11/25/2025 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 12/3/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 12/3/2025 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 12/3/2025 Approved CHRISTOPHER ROJAS
Drywall Nailing 12/9/2025 Approved CHRISTOPHER MORFIN
Final 1/7/2026 OK to Issue CofO CHRISTOPHER ROJAS
Footing/Foundation/Slab 1/7/2026 Approved CHRISTOPHER ROJAS
Green Building Final 1/7/2026 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 1/7/2026 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 1/7/2026 Approved CHRISTOPHER ROJAS