16528-16530 W BIRCHER ST 91344

Certificate Information: 16528-16530 W BIRCHER ST 91344

Application / Permit
25016-20000-24108
Plan Check / Job No.
B25VN22901
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: CONVERT (E) ATTACHED GARAGE TO STATE ADU PER GCS 66323(a)(1). WORK PER ENGINEERED DESIGN.
Permit Issued
Issued on 10/1/2025
Issuing Office
Current Status
Issued on 10/1/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/7/2025 APPLICANT
Assigned to Plan Check Engineer 8/12/2025 MINA HABILI
Corrections Issued 8/12/2025 MINA HABILI
Applicant returned to address corrections 9/17/2025 SAMUEL GONZALEZ
Plan Check Approved 9/30/2025 EDWIN MARTINEZ
Issued 10/1/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/29/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 8/29/2025 BIAINA HARITUNIAN
Sewer availability Cleared 8/29/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 9/3/2025 BIAINA HARITUNIAN
Grading Pre-Inspection Cleared 9/17/2025 MINA HABILI

Contact Information

Contractor Owner-Builder       ,
Engineer Tangonan,, Jeffrey Tolentino; Lic. No.: C83522 17770 CAPE JASMINE RD      CANYON COUNTRY, CA 91387

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/15/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Footing/Foundation/Slab 10/15/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Pre-Inspection 10/15/2025 Partial Approval CHRISTOPHER ROJAS
Underground Mechanical 10/15/2025 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 10/17/2025 Corrections Issued CHRISTOPHER ROJAS
Deputy Drilled-In Anchors 10/20/2025 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 10/22/2025 Approved CHRISTOPHER ROJAS
Underground Mechanical 10/22/2025 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 3/5/2026 Partial Approval CHRISTOPHER ROJAS
ELECTRICAL-Rough 3/5/2026 Approved CHRISTOPHER ROJAS
Green Building Rough 3/5/2026 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 3/5/2026 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Rough 3/5/2026 Corrections Issued CHRISTOPHER ROJAS
Wood Frame 3/5/2026 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 3/12/2026 Approved KEVIN BERBERYAN
Green Building Rough 3/12/2026 Not Ready for Inspection KEVIN BERBERYAN
HVAC-Rough 3/12/2026 Approved KEVIN BERBERYAN
PLUMBING-Rough 3/12/2026 Approved KEVIN BERBERYAN
Insulation 4/13/2026 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 4/13/2026 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 5/5/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Drywall Nailing 5/5/2026 Approved CHRISTOPHER ROJAS
Green Building Rough 5/5/2026 Approved CHRISTOPHER ROJAS
Shower Pan 5/5/2026 Approved CHRISTOPHER ROJAS
Drywall Nailing 5/7/2026 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 5/7/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Shower Pan 5/7/2026 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 6/2/2026 Approved CHRISTOPHER ROJAS