13373 W WINGO ST 91331
Certificate Information: 13373 W WINGO ST 91331
- Application / Permit
- 25016-20000-24012
- Plan Check / Job No.
- B25VN22768
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. Convert (E) Storage to an Accessory Dwelling Unit per LAMC 12.22 A.33(b)(1). All work per WFPP
- Permit Issued
- Issued on 1/3/2026
- Issuing Office
- Current Status
- Issued on 1/3/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/13/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2025 | AMY GUEVARRA |
| Corrections Issued | 8/21/2025 | AMY GUEVARRA |
| Applicant returned to address corrections | 11/21/2025 | AMY GUEVARRA |
| Applicant returned to address corrections | 11/26/2025 | AMY GUEVARRA |
| Plan Check Approved | 1/2/2026 | CAROLEAN BASMA |
| Issued | 1/3/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/3/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 9/3/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 9/3/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 11/20/2025 | SAFA JAVANMARDI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/27/2026 | Partial Inspection | MICHEL ABAJAN |
| Deputy Drilled-In Anchors | 2/26/2026 | Conditional Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 2/27/2026 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 2/27/2026 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 3/11/2026 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 3/11/2026 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 3/11/2026 | Not Ready for Inspection | MICHEL ABAJAN |
| HVAC-Rough | 3/16/2026 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 3/16/2026 | Approved | MICHEL ABAJAN |
| Insulation | 3/19/2026 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 3/24/2026 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 5/21/2026 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Final | 5/29/2026 | Approved | MICHEL ABAJAN |
| Final | 5/29/2026 | Corrections Issued | MICHEL ABAJAN |
| HVAC-Final | 5/29/2026 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 5/29/2026 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 5/29/2026 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 5/29/2026 | Approved | MICHEL ABAJAN |