18599-18601 W STARE ST 91324

Certificate Information: 18599-18601 W STARE ST 91324

Application / Permit
25016-20000-23758
Plan Check / Job No.
B25VN22441
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN Convert existing 2 car garage to new ADU 489 sf per GC 66323(a)(1)
Permit Issued
Issued on 9/5/2025
Issuing Office
Current Status
CofO Issued on 4/10/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/11/2025 APPLICANT
Assigned to Plan Check Engineer 8/14/2025 CARLOS MONTES
Corrections Issued 8/14/2025 CARLOS MONTES
Applicant returned to address corrections 8/22/2025 SAMUEL GONZALEZ
Plan Check Approved 9/3/2025 ADAM HEGAZI
Issued 9/5/2025 APPLICANT
CofO in Progress 4/8/2026 DAVID SCANTLIN
Permit Finaled 4/10/2026 JOHN JANSON
CofO Issued 4/10/2026 JOHN JANSON
Permit Finaled 4/10/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/20/2025 SAFA JAVANMARDI
Sewer availability Cleared 8/20/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 8/21/2025 SAFA JAVANMARDI

Contact Information

Contractor Owner-Builder       ,
Engineer Pinzon,, Eduardo Andres; Lic. No.: C74869 821 W SPRUCE ST      WEST COVINA, CA 91790

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/17/2025 Partial Approval KRISTEN CAUSEY
Deputy Drilled-In Anchors 9/22/2025 Approved DAVID SCANTLIN
Footing/Foundation/Slab 9/22/2025 Approved DAVID SCANTLIN
Sewer 9/25/2025 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 11/12/2025 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Rough 11/12/2025 Partial Approval DAVID SCANTLIN
Green Building Rough 11/12/2025 Not Ready for Inspection DAVID SCANTLIN
HVAC-Rough 11/12/2025 Approved DAVID SCANTLIN
PLUMBING-Rough 11/12/2025 Approved DAVID SCANTLIN
Special/Order Compliance 11/12/2025 Corrections Issued DAVID SCANTLIN
BUILDING-Rough-Frame 11/17/2025 Approved DAVID SCANTLIN
Green Building Rough 11/17/2025 Approved DAVID SCANTLIN
Insulation 11/17/2025 Approved DAVID SCANTLIN
Interior/Exterior Lathing 11/17/2025 Partial Approval DAVID SCANTLIN
Rough-Elec/Plmb/HVAC 11/17/2025 Approved DAVID SCANTLIN
Drywall Nailing 11/26/2025 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 11/26/2025 Approved KRISTEN CAUSEY
Shower Pan 11/26/2025 Approved KRISTEN CAUSEY
Final 2/17/2026 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 2/17/2026 Not Ready for Inspection CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 2/17/2026 SGSOV Not Ready CHRIS CHRISTENSEN
Smoke Detectors 2/17/2026 Approved CHRIS CHRISTENSEN
Final 3/3/2026 Not Ready for Inspection DAVID SCANTLIN
Green Building Final 3/3/2026 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 3/3/2026 SGSOV Not Ready DAVID SCANTLIN
Final 3/4/2026 Not Ready for Inspection DAVID SCANTLIN
Final 4/7/2026 OK to Issue CofO DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 4/7/2026 SGSOV Approved DAVID SCANTLIN
Service/Power Release 4/7/2026 Approved DAVID SCANTLIN