10040-10040 1/2 N MASON AVE 91311

Certificate Information: 10040-10040 1/2 N MASON AVE 91311

Application / Permit
25016-20000-23626
Plan Check / Job No.
B25VN22273
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
EPLAN. CONVERT EXISTING ATTACHED GARAGE INTO AN ADDITIONAL DWELLING UNIT PER SB9 TWO UNIT DEVELOPMENT CA GOVT CODE 65852.21. ***REQD TO BE SPRINKLERED PER NFPA 13D***
Permit Issued
Issued on 11/12/2025
Issuing Office
Current Status
Issued on 11/12/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/1/2025 APPLICANT
Assigned to Plan Check Engineer 8/7/2025 MICHAEL LOPEZ
Corrections Issued 8/18/2025 MICHAEL LOPEZ
Quality Review Completed 8/19/2025 PRANITA SHAH
Applicant returned to address corrections 9/5/2025 MICHAEL LOPEZ
Applicant returned to address corrections 10/3/2025 MICHAEL LOPEZ
Applicant returned to address corrections 10/21/2025 MICHAEL LOPEZ
Plan Check Approved 11/7/2025 MICHAEL LOPEZ
Issued 11/12/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/14/2025 DERRICK MAGEE
Senate Bill 9 Cleared 8/14/2025 DAVID URITA
Sewer availability Cleared 8/17/2025 DERRICK MAGEE
Eng Process Fee Ord 176,300 Cleared 8/18/2025 DERRICK MAGEE

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor Fire And Casualty Company; Lic. No.: 990126-B       ,
Contractor Four Seasons Builders Inc; Lic. No.: 990126-B       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/16/2025 Approved DAVID SCANTLIN
PLUMBING-Rough 12/29/2025 Partial Approval KRISTEN CAUSEY
ELECTRICAL-Rough 2/11/2026 Approved DAVID SCANTLIN
HVAC-Rough 2/11/2026 Not Ready for Inspection DAVID SCANTLIN
PLUMBING-Rough 2/11/2026 Approved DAVID SCANTLIN
Wood Frame 2/11/2026 Not Ready for Inspection DAVID SCANTLIN
Drywall Nailing 2/18/2026 Partial Approval KRISTEN CAUSEY
HVAC-Rough 2/18/2026 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 2/24/2026 Corrections Issued DAVID SCANTLIN
Interior/Exterior Lathing 2/24/2026 Partial Approval DAVID SCANTLIN
BUILDING-Rough-Frame 3/23/2026 Not Ready for Inspection JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 3/23/2026 Corrections Issued JACK KARGODORIAN
Green Building Rough 3/23/2026 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 3/24/2026 Approved JACK KARGODORIAN
Wood Frame 3/24/2026 Approved JACK KARGODORIAN
Drywall Nailing 3/31/2026 Approved JACK KARGODORIAN