6502 W 5TH ST 90048

Certificate Information: 6502 W 5TH ST 90048

Application / Permit
25016-20000-23544
Plan Check / Job No.
B25VN22148
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE TO NEW ACCESORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c), (d), and (g)
Permit Issued
Issued on 11/18/2025
Issuing Office
West Los Angeles
Current Status
CofO Issued on 5/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/1/2025 APPLICANT
Assigned to Plan Check Engineer 8/7/2025 SELLA BENYAMIN
Corrections Issued 8/12/2025 SELLA BENYAMIN
Quality Review Completed 8/15/2025 STEVEN KIM
Building Plans Picked Up 8/19/2025 APPLICANT
Plan Check Approved 11/18/2025 SELLA BENYAMIN
Issued 11/18/2025 APPLICANT
CofO in Progress 5/12/2026 KIRK SANDERS
Permit Finaled 5/28/2026 RICHARD STEINBACH
CofO Issued 5/28/2026 RICHARD STEINBACH
Permit Finaled 5/28/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 8/21/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 8/21/2025 SAFA JAVANMARDI
Sewer availability Cleared 8/21/2025 SAFA JAVANMARDI
Construction near power lines Cleared 11/3/2025 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Yench,, Stephen Henry; Lic. No.: C33731 1691 TAMARRON DR      CORONA, CA 92883

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/5/2025 Approved EVAN COOPER
Excavation/Setback/Form/Re-Bar 12/5/2025 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 12/12/2025 Corrections Issued EVAN COOPER
Green Building Rough 12/12/2025 Not Ready for Inspection EVAN COOPER
METHANE-Rough 12/12/2025 Approved EVAN COOPER
Deputy Wood Construction 12/15/2025 Conditional Approval DAVID FEILER
ELECTRICAL-Rough 12/29/2025 Approved MICHAEL ALLEN
Gas Test 12/29/2025 Approved MICHAEL ALLEN
HVAC-Rough 12/29/2025 Approved MICHAEL ALLEN
PLUMBING-Rough 12/29/2025 Approved MICHAEL ALLEN
Special/Order Compliance 12/29/2025 Partial Inspection DAKOTA LOW
BUILDING-Rough-Frame 1/6/2026 Partial Approval WILBER ROSALES
Interior/Exterior Lathing 1/6/2026 Partial Approval WILBER ROSALES
Special/Order Compliance 1/6/2026 Partial Inspection DAKOTA LOW
BUILDING-Rough-Frame 1/13/2026 Approved WILBER ROSALES
Green Building Rough 1/13/2026 Approved WILBER ROSALES
Insulation 1/13/2026 Corrections Issued WILBER ROSALES
Drywall Nailing 1/26/2026 Approved MICHAEL ALLEN
Shower Pan 1/26/2026 Approved MICHAEL ALLEN
Interior/Exterior Lathing 1/28/2026 Approved WILBER ROSALES
ELECTRICAL-Final 4/21/2026 Approved WILBER ROSALES
HVAC-Final 4/21/2026 Corrections Issued WILBER ROSALES
PLUMBING-Final 4/21/2026 Approved WILBER ROSALES
Final 5/11/2026 OK to Issue CofO KIRK SANDERS
Green Building Final 5/11/2026 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 5/11/2026 SGSOV Approved KIRK SANDERS
Smoke Detectors 5/11/2026 Approved KIRK SANDERS