15713-15715 W TULSA ST 91344

Certificate Information: 15713-15715 W TULSA ST 91344

Application / Permit
25016-20000-23002
Plan Check / Job No.
B25VN21528
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. GARAGE CONVERSION TO JR ADU TO (E) SFD
Permit Issued
Issued on 8/15/2025
Issuing Office
Current Status
CofO Issued on 3/3/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/26/2025 APPLICANT
Assigned to Plan Check Engineer 7/30/2025 DANIEL SANJUAN
Corrections Issued 7/30/2025 DANIEL SANJUAN
Applicant returned to address corrections 8/5/2025 NEHEMIAS RAMOS
Applicant returned to address corrections 8/12/2025 NEHEMIAS RAMOS
Applicant returned to address corrections 8/13/2025 NEHEMIAS RAMOS
Plan Check Approved 8/15/2025 FERNANDO FLORES
Issued 8/15/2025 APPLICANT
CofO in Progress 2/19/2026 CHRISTOPHER ROJAS
Permit Finaled 3/3/2026 RUBEN SALAS
CofO Issued 3/3/2026 RUBEN SALAS
Permit Finaled 3/3/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/6/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 8/6/2025 SAFA JAVANMARDI
Sewer availability Cleared 8/6/2025 SAFA JAVANMARDI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/20/2025 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Rough 8/20/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Special/Order Compliance 8/20/2025 Corrections Issued CHRISTOPHER ROJAS
Excavation/Setback/Form/Re-Bar 8/21/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Excavation/Setback/Form/Re-Bar 8/25/2025 Not Ready for Inspection WAYNE REGESTER
PLUMBING-Rough 8/25/2025 Approved WAYNE REGESTER
Deputy Drilled-In Anchors 8/27/2025 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 8/27/2025 Corrections Issued NICHOLAS TROWBRIDGE
Footing/Foundation/Slab 9/2/2025 Approved NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 10/2/2025 Corrections Issued NICHOLAS TROWBRIDGE
Green Building Rough 10/2/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
MERV13>=Rough 10/2/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Rough-Elec/Plmb/HVAC 10/2/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 10/7/2025 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 10/7/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Rough 10/7/2025 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 10/7/2025 Corrections Issued CHRISTOPHER ROJAS
Interior/Exterior Lathing 10/7/2025 Not Ready for Inspection CHRISTOPHER ROJAS
MERV13>=Rough 10/7/2025 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 10/7/2025 Corrections Issued CHRISTOPHER ROJAS
BUILDING-Rough-Frame 10/10/2025 Partial Approval CHRISTOPHER ROJAS
ELECTRICAL-Rough 10/10/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Rough 10/10/2025 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 10/10/2025 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 10/10/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Insulation 10/15/2025 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 10/21/2025 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 10/23/2025 Approved CHRISTOPHER ROJAS
Drywall Nailing 10/27/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Drywall Nailing 10/30/2025 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 10/30/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Interior/Exterior Lathing 11/5/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Interior/Exterior Lathing 11/13/2025 Corrections Issued CHRISTOPHER ROJAS
Interior/Exterior Lathing 11/17/2025 Partial Approval CHRISTOPHER ROJAS
Interior/Exterior Lathing 11/19/2025 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 1/5/2026 Approved CHRISTOPHER ROJAS
Green Building Final 1/5/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Rough 1/5/2026 Approved CHRISTOPHER ROJAS
MERV13>=Final 1/5/2026 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 1/5/2026 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 1/5/2026 Partial Approval CHRISTOPHER ROJAS
ELECTRICAL-Final 1/6/2026 Corrections Issued CHRISTOPHER ROJAS
Final 1/6/2026 Corrections Issued CHRISTOPHER ROJAS
HVAC-Final 1/6/2026 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Final 1/6/2026 Corrections Issued CHRISTOPHER ROJAS
Final 1/12/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Final 1/12/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Smoke Detectors 1/12/2026 Approved CHRISTOPHER ROJAS
Pre-Inspection 1/15/2026 Approved CHRISTOPHER ROJAS
Final 1/22/2026 Corrections Issued JENNIFER RABUCHIN
Green Building Final 1/22/2026 Approved JENNIFER RABUCHIN
Final 1/29/2026 Corrections Issued KIRK SANDERS
Final 2/3/2026 No Access for Inspection CHRISTOPHER ROJAS
Final 2/19/2026 OK to Issue CofO CHRISTOPHER ROJAS