8323 N OUTLAND VIEW DR 91352
Certificate Information: 8323 N OUTLAND VIEW DR 91352
- Application / Permit
- 25016-20000-22994
- Plan Check / Job No.
- B25VN21521
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DET. GARAGE TO ACCESSORY DWELLING UNIT PER GC 66323(a)(1) PER WFPP.
- Permit Issued
- Issued on 8/14/2025
- Issuing Office
- Current Status
- CofO Issued on 4/10/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/25/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/31/2025 | JESSE ARELLANO |
| Corrections Issued | 8/2/2025 | JESSE ARELLANO |
| Building Plans Picked Up | 8/4/2025 | APPLICANT |
| Issued | 8/14/2025 | APPLICANT |
| CofO in Progress | 2/27/2026 | DAVID ANDERSON |
| Permit Finaled | 4/10/2026 | RUBEN SALAS |
| CofO Issued | 4/10/2026 | RUBEN SALAS |
| Permit Finaled | 4/10/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/4/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 8/4/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 8/4/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 8/4/2025 | LEE GUILBEAUX |
| Grading Pre-Inspection | Cleared | 8/12/2025 | CHARLES POWELL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/19/2025 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 11/12/2025 | Partial Approval | DAVID ANDERSON |
| ELECTRICAL-Rough | 11/12/2025 | Approved | DAVID ANDERSON |
| HVAC-Rough | 11/12/2025 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 11/12/2025 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 11/21/2025 | Approved | DAVID ANDERSON |
| Green Building Rough | 11/21/2025 | Approved | DAVID ANDERSON |
| Insulation | 11/21/2025 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 11/21/2025 | Partial Approval | DAVID ANDERSON |
| MERV13>=Rough | 11/21/2025 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/25/2025 | Approved | DAVID ANDERSON |
| Drywall Nailing | 12/5/2025 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 12/5/2025 | Approved | MICHAEL CORTEZ |
| Shower Pan | 12/5/2025 | Not Ready for Inspection | MICHAEL CORTEZ |
| Shower Pan | 12/8/2025 | Approved | LOUIS ESCOTO |
| Final | 2/23/2026 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 2/23/2026 | Approved | DAVID ANDERSON |
| MERV13>=Final | 2/23/2026 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 2/23/2026 | SGSOV Approved | DAVID ANDERSON |
| Smoke Detectors | 2/23/2026 | Approved | DAVID ANDERSON |
| Final | 2/26/2026 | OK to Issue CofO | DAVID ANDERSON |