1914 S WESTGATE AVE 90025
Certificate Information: 1914 S WESTGATE AVE 90025
- Application / Permit
- 25016-20000-22739
- Plan Check / Job No.
- B25VN21199
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GC 66323(a)(1).
- Permit Issued
- Issued on 8/1/2025
- Issuing Office
- Current Status
- CofO Issued on 5/22/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/23/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/28/2025 | ARAMIK SHAHMIRZAIAN |
| Corrections Issued | 7/28/2025 | ARAMIK SHAHMIRZAIAN |
| Plan Check Approved | 8/1/2025 | ISIS ARGUETA |
| Issued | 8/1/2025 | APPLICANT |
| Building Plans Picked Up | 8/1/2025 | APPLICANT |
| CofO in Progress | 5/18/2026 | MICHAEL ALLEN |
| Permit Finaled | 5/22/2026 | RICHARD STEINBACH |
| CofO Issued | 5/22/2026 | RICHARD STEINBACH |
| Permit Finaled | 5/22/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 7/30/2025 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 7/30/2025 | JESSICA OPINION |
| Sewer availability | Cleared | 7/30/2025 | JESSICA OPINION |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Arakelyan,, Aram; Lic. No.: C82796 | 145 S GLENOAKS BI 328 BURBANK, CA 91502 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/25/2025 | No Access for Inspection | ARAM AVEDISIAN |
| Pre-Inspection | 9/26/2025 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 9/30/2025 | Partial Approval | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 10/7/2025 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Rough | 10/21/2025 | Corrections Issued | MICHAEL ALLEN |
| HVAC-Rough | 10/21/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Rough | 10/21/2025 | Corrections Issued | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2025 | Partial Approval | MICHAEL ALLEN |
| Insulation | 10/29/2025 | Corrections Issued | MICHAEL ALLEN |
| Interior/Exterior Lathing | 10/29/2025 | Partial Approval | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 10/31/2025 | Conditional Approval | MICHAEL ALLEN |
| Green Building Rough | 10/31/2025 | Conditional Approval | MICHAEL ALLEN |
| Insulation | 10/31/2025 | Approved | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2025 | Approved | MICHAEL ALLEN |
| Drywall Nailing | 11/7/2025 | Corrections Issued | MICHAEL ALLEN |
| Drywall Nailing | 11/12/2025 | Approved | MICHAEL ALLEN |
| Insulation | 11/12/2025 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 11/12/2025 | Partial Approval | MICHAEL ALLEN |
| Shower Pan | 11/12/2025 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 11/19/2025 | Partial Approval | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 11/19/2025 | SGSOV Approved | MICHAEL ALLEN |
| Sewer | 1/27/2026 | Approved | RYAN SALAZAR |
| Underground Mechanical | 1/27/2026 | Approved | RYAN SALAZAR |
| Service/Power Release | 1/30/2026 | Not Ready for Inspection | MICHAEL ALLEN |
| ELECTRICAL-Final | 3/12/2026 | Corrections Issued | WILBER ROSALES |
| HVAC-Final | 3/12/2026 | Corrections Issued | WILBER ROSALES |
| PLUMBING-Final | 3/12/2026 | Corrections Issued | WILBER ROSALES |
| Service/Power Release | 3/12/2026 | Not Ready for Inspection | WILBER ROSALES |
| BUILDING-Rough-Frame | 4/2/2026 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Final | 4/2/2026 | Corrections Issued | MICHAEL ALLEN |
| Final | 4/2/2026 | Corrections Issued | MICHAEL ALLEN |
| Green Building Final | 4/2/2026 | Approved | MICHAEL ALLEN |
| Green Building Rough | 4/2/2026 | Approved | MICHAEL ALLEN |
| HVAC-Final | 4/2/2026 | Corrections Issued | MICHAEL ALLEN |
| PLUMBING-Final | 4/2/2026 | Corrections Issued | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 4/2/2026 | SGSOV Approved | MICHAEL ALLEN |
| Smoke Detectors | 4/2/2026 | Corrections Issued | MICHAEL ALLEN |
| ELECTRICAL-Final | 4/8/2026 | Approved | WILBER ROSALES |
| Gas Test | 4/8/2026 | Approved | WILBER ROSALES |
| HVAC-Final | 4/8/2026 | Not Ready for Inspection | WILBER ROSALES |
| PLUMBING-Final | 4/8/2026 | Approved | WILBER ROSALES |
| Service/Power Release | 4/8/2026 | Not Ready for Inspection | WILBER ROSALES |
| Final | 4/14/2026 | Corrections Issued | EVAN COOPER |
| Smoke Detectors | 4/14/2026 | Approved | EVAN COOPER |
| Final | 5/5/2026 | Corrections Issued | MICHAEL LEWIS |
| Final | 5/13/2026 | Conditional Approval | ANTHONY EGSON |
| HVAC-Final | 5/13/2026 | Approved | ANTHONY EGSON |
| Service/Power Release | 5/13/2026 | Approved | ANTHONY EGSON |
| Final | 5/15/2026 | OK to Issue CofO | MICHAEL ALLEN |