7822 N TAMPA AVE 91335

Certificate Information: 7822 N TAMPA AVE 91335

Application / Permit
25016-20000-21945
Plan Check / Job No.
B25VN20322
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT EX ATTACHED 1-CAR CARPORT INTO BEDROOM. ALL WORK PER WFPP.
Permit Issued
Issued on 8/15/2025
Issuing Office
Valley
Current Status
CofO in Progress on 11/3/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/16/2025 APPLICANT
Corrections Issued 7/22/2025 HAYATO TSUCHIYA
Assigned to Plan Check Engineer 7/23/2025 HAYATO TSUCHIYA
Building Plans Picked Up 7/24/2025 APPLICANT
Corrections Issued 8/11/2025 HAYATO TSUCHIYA
Applicant returned to address corrections 8/13/2025 NAREG ATARIAN
Plan Check Approved 8/15/2025 ISIS ARGUETA
Issued 8/15/2025 APPLICANT
CofO in Progress 11/3/2025 JUAN ALVARADO

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/4/2025 CARLOS AGUILERA
Sewer availability Cleared 8/4/2025 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/21/2025 Conditional Approval ARUTYUN MADATYAN
ELECTRICAL-Rough 9/4/2025 Not Ready for Inspection JUAN ALVARADO
Excavation/Setback/Form/Re-Bar 9/4/2025 Corrections Issued JUAN ALVARADO
PLUMBING-Rough 9/4/2025 Corrections Issued JUAN ALVARADO
Wood Frame 9/4/2025 Corrections Issued JUAN ALVARADO
Footing/Foundation/Slab 9/8/2025 Partial Approval ARUTYUN MADATYAN
Green Building Rough 9/8/2025 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Rough 9/8/2025 Approved ARUTYUN MADATYAN
Rough-Elec/Plmb/HVAC 9/8/2025 Not Ready for Inspection ARUTYUN MADATYAN
BUILDING-Rough-Frame 9/12/2025 Corrections Issued JUAN ALVARADO
ELECTRICAL-Rough 9/12/2025 Approved JUAN ALVARADO
Green Building Rough 9/12/2025 Not Ready for Inspection JUAN ALVARADO
BUILDING-Rough-Frame 9/17/2025 Partial Approval JUAN ALVARADO
Green Building Rough 9/17/2025 No Access for Inspection JUAN ALVARADO
Interior/Exterior Lathing 9/22/2025 Corrections Issued JUAN ALVARADO
Shower Pan 9/22/2025 Approved JUAN ALVARADO
BUILDING-Rough-Frame 9/24/2025 Approved JUAN ALVARADO
Green Building Rough 9/24/2025 Approved JUAN ALVARADO
Insulation 9/24/2025 Approved JUAN ALVARADO
Interior/Exterior Lathing 9/24/2025 Approved JUAN ALVARADO
Drywall Nailing 9/26/2025 Approved JUAN ALVARADO
Interior/Exterior Lathing 9/26/2025 Approved JUAN ALVARADO
Final 10/24/2025 Corrections Issued JUAN ALVARADO
Green Building Final 10/24/2025 Approved JUAN ALVARADO
HVAC-Final 10/24/2025 Approved JUAN ALVARADO
PLUMBING-Final 10/24/2025 Approved JUAN ALVARADO
Smoke Detectors 10/24/2025 Not Ready for Inspection JUAN ALVARADO
ELECTRICAL-Final 10/30/2025 Approved JUAN ALVARADO
Final 10/30/2025 OK to Issue CofO JUAN ALVARADO
Smoke Detectors 10/30/2025 Approved JUAN ALVARADO
Pre-Inspection 11/12/2025 Corrections Issued JUAN ALVARADO
Special/Order Compliance 11/12/2025 Corrections Issued JUAN ALVARADO