805 E 25TH ST 90011
Certificate Information: 805 E 25TH ST 90011
- Application / Permit
- 25016-20000-21884
- Plan Check / Job No.
- B25VN20270
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (2) Duplex
- Work Description
- PARTIAL FIRE DAMAGED REPAIR OF AN EXISTING DUPLEX FIRST FLOOR.
- Permit Issued
- Issued on 10/28/2025
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 4/8/2026
Permit Application Status History
| Submitted | 7/16/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/18/2025 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 7/19/2025 | MIROOSH KHACHATOORIAN |
| Building Plans Picked Up | 7/23/2025 | APPLICANT |
| Applicant returned to address corrections | 9/10/2025 | MOHAMMAD ESMAILI |
| Plan Check Approved | 9/19/2025 | ISIS ARGUETA |
| Issued | 10/28/2025 | APPLICANT |
| Permit Finaled | 4/7/2026 | JAMES POWERS |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 9/15/2025 | ARIC DEFUSCO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kardjian,, Vahe Matios; Lic. No.: C40821 | 1112 W BURBANK BLVD STE 301 BURBANK, CA 91506 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/17/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Pre-Inspection | 1/23/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Pre-Inspection | 1/28/2026 | Partial Inspection | ALFREDO LOPEZ |
| Footing/Foundation/Slab | 2/4/2026 | Partial Inspection | REGINA MENDEZ |
| Deputy Wood Construction | 2/12/2026 | Partial Approval | IAN BLINN |
| Wood Frame | 2/12/2026 | Partial Approval | IAN BLINN |
| Insulation | 2/17/2026 | Partial Approval | ALFREDO LOPEZ |
| Interior/Exterior Lathing | 2/17/2026 | Corrections Issued | ALFREDO LOPEZ |
| Wood Frame | 2/20/2026 | Approved | ALFREDO LOPEZ |
| Drywall Nailing | 2/24/2026 | Approved | ALFREDO LOPEZ |
| Interior/Exterior Lathing | 2/24/2026 | Approved | ALFREDO LOPEZ |
| Final | 3/17/2026 | Partial Inspection | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 3/17/2026 | SGSOV Not Ready | ALFREDO LOPEZ |
| Smoke Detectors | 3/17/2026 | Not Ready for Inspection | ALFREDO LOPEZ |
| Final | 4/6/2026 | Not Ready for Inspection | JAMES POWERS |
| SGSOV-Seismic Gas S/O Valve | 4/6/2026 | SGSOV Approved | JAMES POWERS |
| Smoke Detectors | 4/6/2026 | Approved | JAMES POWERS |
| Final | 4/7/2026 | Permit Finaled | JAMES POWERS |