13114 W ADDISON ST 91423

Certificate Information: 13114 W ADDISON ST 91423

Application / Permit
25016-20000-21763
Plan Check / Job No.
B25VN20125
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL TO RELOCATE KITCHEN AND DEN. REMOVE AND FILL IN TWO WINDOWS. ENCLOSE AND CONVERT 8'-5" x 6'-9" PORTION OF COVERED PORCH TO ENLARGE DEN. CONVERT PORTION OF DINING ROOM TO HALF BATHROOM. REMODEL TWO EXISTING BATHROOMS. CONVERT 5'-4" x 8'-5" PORITON OF ATT. GARAGE INTO HALF BATHROOM. ALL WORK PER ENG.
Permit Issued
Issued on 8/4/2025
Issuing Office
Valley
Current Status
CofO Issued on 3/18/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/15/2025 APPLICANT
Assigned to Plan Check Engineer 7/18/2025 JEROME MAGAT PALMA
Corrections Issued 7/18/2025 JEROME MAGAT PALMA
Building Plans Picked Up 7/24/2025 APPLICANT
Applicant returned to address corrections 7/31/2025 ANGELICA DAVE
Issued 8/4/2025 APPLICANT
CofO in Progress 2/19/2026 MATTHEW NELSON
Permit Finaled 3/18/2026 RUBEN SALAS
CofO Issued 3/18/2026 RUBEN SALAS
Permit Finaled 3/18/2026 RUBEN SALAS

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Kdn Builders Group Inc; Lic. No.: 1120729-B 13240 MCCORMICK STREET      SHERMAN OAKS, CA 91401
Engineer Braun,, Jason; Lic. No.: C70948 14390 SHAWNEE ST      MOORPARK, CA 93021

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 9/2/2025 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 9/3/2025 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 9/9/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Interior/Exterior Lathing 9/9/2025 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 9/9/2025 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 9/12/2025 Approved OGANES TARAKHCHYAN
Green Building Rough 9/12/2025 Approved OGANES TARAKHCHYAN
HVAC-Rough 9/12/2025 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 9/12/2025 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 9/12/2025 Approved OGANES TARAKHCHYAN
Shower Pan 9/15/2025 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 9/22/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Insulation 9/22/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Insulation 9/23/2025 Not Ready for Inspection WAYNE REGESTER
BUILDING-Rough-Frame 9/24/2025 Approved OGANES TARAKHCHYAN
Insulation 9/26/2025 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 9/26/2025 Approved OGANES TARAKHCHYAN
Drywall Nailing 10/16/2025 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 1/30/2026 Approved WAYNE REGESTER
Final 1/30/2026 Not Ready for Inspection WAYNE REGESTER
Green Building Final 1/30/2026 Approved WAYNE REGESTER
HVAC-Final 1/30/2026 Approved WAYNE REGESTER
PLUMBING-Final 1/30/2026 Approved WAYNE REGESTER
SGSOV-Seismic Gas S/O Valve 1/30/2026 SGSOV Approved WAYNE REGESTER
Smoke Detectors 1/30/2026 Approved WAYNE REGESTER
Final 2/11/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 2/18/2026 OK to Issue CofO MATTHEW NELSON