13114 W ADDISON ST 91423
Certificate Information: 13114 W ADDISON ST 91423
- Application / Permit
- 25016-20000-21763
- Plan Check / Job No.
- B25VN20125
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO RELOCATE KITCHEN AND DEN. REMOVE AND FILL IN TWO WINDOWS. ENCLOSE AND CONVERT 8'-5" x 6'-9" PORTION OF COVERED PORCH TO ENLARGE DEN. CONVERT PORTION OF DINING ROOM TO HALF BATHROOM. REMODEL TWO EXISTING BATHROOMS. CONVERT 5'-4" x 8'-5" PORITON OF ATT. GARAGE INTO HALF BATHROOM. ALL WORK PER ENG.
- Permit Issued
- Issued on 8/4/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/18/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/15/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/18/2025 | JEROME MAGAT PALMA |
| Corrections Issued | 7/18/2025 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 7/24/2025 | APPLICANT |
| Applicant returned to address corrections | 7/31/2025 | ANGELICA DAVE |
| Issued | 8/4/2025 | APPLICANT |
| CofO in Progress | 2/19/2026 | MATTHEW NELSON |
| Permit Finaled | 3/18/2026 | RUBEN SALAS |
| CofO Issued | 3/18/2026 | RUBEN SALAS |
| Permit Finaled | 3/18/2026 | RUBEN SALAS |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Kdn Builders Group Inc; Lic. No.: 1120729-B | 13240 MCCORMICK STREET SHERMAN OAKS, CA 91401 |
| Engineer | Braun,, Jason; Lic. No.: C70948 | 14390 SHAWNEE ST MOORPARK, CA 93021 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 9/2/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 9/3/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 9/9/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 9/9/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 9/9/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 9/12/2025 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 9/12/2025 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 9/12/2025 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 9/12/2025 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 9/12/2025 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 9/15/2025 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 9/22/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Insulation | 9/22/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Insulation | 9/23/2025 | Not Ready for Inspection | WAYNE REGESTER |
| BUILDING-Rough-Frame | 9/24/2025 | Approved | OGANES TARAKHCHYAN |
| Insulation | 9/26/2025 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 9/26/2025 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 10/16/2025 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 1/30/2026 | Approved | WAYNE REGESTER |
| Final | 1/30/2026 | Not Ready for Inspection | WAYNE REGESTER |
| Green Building Final | 1/30/2026 | Approved | WAYNE REGESTER |
| HVAC-Final | 1/30/2026 | Approved | WAYNE REGESTER |
| PLUMBING-Final | 1/30/2026 | Approved | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 1/30/2026 | SGSOV Approved | WAYNE REGESTER |
| Smoke Detectors | 1/30/2026 | Approved | WAYNE REGESTER |
| Final | 2/11/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 2/18/2026 | OK to Issue CofO | MATTHEW NELSON |