511 1/2 S LUCERNE BLVD 90020
Certificate Information: 511 1/2 S LUCERNE BLVD 90020
- Application / Permit
- 25016-20000-21701
- Plan Check / Job No.
- B25VN20029
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT ENTIRE ATTIC SPACE WITHIN EX ACCESSORY DWELLING UNIT (ADU) INTO 2ND FLOOR LOFT. DEMO EX CLOSET AT 1ST FLOOR FOR NEW STAIRS TO NEW 2ND FLOOR LOFT.
- Permit Issued
- Issued on 3/6/2026
- Issuing Office
- Metro
- Current Status
- Issued on 3/6/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/15/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/18/2025 | HAYATO TSUCHIYA |
| Corrections Issued | 7/23/2025 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 7/29/2025 | APPLICANT |
| Plan Check Approved | 12/18/2025 | ALEC MOUSAKHANIAN |
| Issued | 3/6/2026 | APPLICANT |
Permit Application Clearance Information
| CPC | Cleared | 9/5/2025 | DANIEL CORONADO |
| CPC | Cleared | 9/5/2025 | DANIEL CORONADO |
| CPC | Cleared | 9/5/2025 | DANIEL CORONADO |
| Miscellaneous | Cleared | 9/5/2025 | DANIEL CORONADO |
| Miscellaneous | Cleared | 9/5/2025 | DANIEL CORONADO |
| Miscellaneous | Cleared | 9/5/2025 | DANIEL CORONADO |
| Miscellaneous | Cleared | 9/5/2025 | DANIEL CORONADO |
| Miscellaneous | Cleared | 9/5/2025 | DANIEL CORONADO |
| ZI | Cleared | 9/5/2025 | DANIEL CORONADO |
| Sewer availability | Cleared | 9/13/2025 | DERRICK MAGEE |
| Eng Process Fee Ord 176,300 | Cleared | 9/15/2025 | DERRICK MAGEE |
| Construction near power lines | Cleared | 10/22/2025 | RIDWAN HARDY |
| HPOZ | Cleared | 10/29/2025 | DAMIAN GATTO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khanjian,, John Hovik; Lic. No.: C51609 | 326 S. SPARKS STREET BURBANK, CA 91506 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Barrier | 3/19/2026 | No Access for Inspection | RONNIE MINDANAO |
| METHANE-Subgrade | 3/19/2026 | No Access for Inspection | RONNIE MINDANAO |
| Footing/Foundation/Slab | 3/23/2026 | Corrections Issued | RONNIE MINDANAO |
| Footing/Foundation/Slab | 4/3/2026 | Conditional Approval | JOSH MEISTER |
| METHANE-Barrier | 4/3/2026 | Approved | JOSH MEISTER |
| METHANE-Subgrade | 4/3/2026 | Approved | JOSH MEISTER |
| BUILDING-Rough-Frame | 6/8/2026 | Not Ready for Inspection | RONNIE MINDANAO |
| ELECTRICAL-Rough | 6/8/2026 | Not Ready for Inspection | RONNIE MINDANAO |
| Green Building Rough | 6/8/2026 | Not Ready for Inspection | RONNIE MINDANAO |
| HVAC-Rough | 6/8/2026 | Corrections Issued | RONNIE MINDANAO |
| METHANE-Rough | 6/8/2026 | Approved | RONNIE MINDANAO |
| PLUMBING-Rough | 6/8/2026 | Approved | RONNIE MINDANAO |