4559 N MORELLA AVE 91607
Certificate Information: 4559 N MORELLA AVE 91607
- Application / Permit
- 25016-20000-21626
- Plan Check / Job No.
- B25VN19940
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO EX. SFD. DEMO WALLS BETWEEN KITCHEN/DINING/HALLWAY/FAMILY RM PER PLAN. REMODEL EX BATHRMS AND KITCHEN. CONVERT CLOSET TO LAUNDRY RM.
- Permit Issued
- Issued on 8/15/2025
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 12/8/2025
Permit Application Status History
| Submitted | 7/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/18/2025 | HAYATO TSUCHIYA |
| Corrections Issued | 7/19/2025 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 7/21/2025 | APPLICANT |
| Plan Check Approved | 8/15/2025 | ROSENDO MEDINA |
| Issued | 8/15/2025 | APPLICANT |
| Permit Finaled | 12/5/2025 | ROBERTO PALACIOS-LOPEZ |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/30/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 7/30/2025 | RYAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grandhi,, Venkata Rohit; Lic. No.: C88709 | 7823 BOXWOOD CT HIGHLAND, CA 92346 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 9/9/2025 | Partial Approval | JAVIER RAMOS JR |
| Excavation/Setback/Form/Re-Bar | 9/9/2025 | Partial Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 9/9/2025 | Partial Approval | JAVIER RAMOS JR |
| MERV13>=Rough | 9/9/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 9/9/2025 | Partial Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 9/23/2025 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 9/23/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Shower Pan | 9/23/2025 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 9/24/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 9/30/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Rough | 9/30/2025 | Partial Inspection | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 9/30/2025 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 10/7/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 10/7/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 10/7/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 10/8/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 10/8/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| HVAC-Rough | 10/8/2025 | Approved | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 10/8/2025 | Approved | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 10/15/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 10/15/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 10/29/2025 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 10/29/2025 | Approved | JAVIER RAMOS JR |
| Insulation | 10/29/2025 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 10/29/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 11/18/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 11/18/2025 | Corrections Issued | JACK KARGODORIAN |
| HVAC-Final | 11/18/2025 | Approved | JACK KARGODORIAN |
| MERV13>=Final | 11/18/2025 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 11/18/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 11/18/2025 | SGSOV Not Ready | JACK KARGODORIAN |
| Smoke Detectors | 11/18/2025 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 12/5/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 12/5/2025 | Permit Finaled | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 12/5/2025 | Partial Inspection | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 12/5/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 12/5/2025 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |