10825 N MCVINE AVE 91040

Certificate Information: 10825 N MCVINE AVE 91040

Application / Permit
25016-20000-21572
Plan Check / Job No.
B25VN19872
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 66323(a)(1)
Permit Issued
Issued on 8/13/2025
Issuing Office
Current Status
CofO Issued on 3/12/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/14/2025 APPLICANT
Assigned to Plan Check Engineer 7/17/2025 MADISON ODELL
Corrections Issued 7/17/2025 MADISON ODELL
Plan Check Approved 8/12/2025 GURUNATH NESARAJAH
Issued 8/13/2025 APPLICANT
CofO in Progress 2/5/2026 NICHOLAS TROWBRIDGE
Permit Finaled 3/12/2026 RUBEN SALAS
CofO Issued 3/12/2026 RUBEN SALAS
Permit Finaled 3/12/2026 RUBEN SALAS

Permit Application Clearance Information

Grading Pre-Inspection Cleared 7/23/2025 ALEXANDER HELFER
Address approval Cleared 7/25/2025 TAL SHEMEN
Sewer availability Cleared 7/25/2025 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 8/3/2025 TAL SHEMEN

Contact Information

Contractor Owner-Builder       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: C93079 15445 VENTURA BLVD #63      SHERMAN OAKS, CA 91403

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/25/2025 Partial Inspection WILLIAM WREN
Deputy Drilled-In Anchors 10/1/2025 Conditional Approval WILLIAM WREN
Underground Mechanical 10/2/2025 Partial Approval WILLIAM WREN
Footing/Foundation/Slab 10/15/2025 Approved WILLIAM WREN
HVAC-Rough 10/15/2025 Approved WILLIAM WREN
PLUMBING-Rough 10/15/2025 Approved WILLIAM WREN
Sewer 10/15/2025 Approved WILLIAM WREN
ELECTRICAL-Rough 10/24/2025 Approved MISAEL ESPARZA
PLUMBING-Rough 10/24/2025 Partial Inspection MISAEL ESPARZA
Insulation 11/5/2025 Partial Approval KEVIN BERBERYAN
Wood Frame 11/5/2025 Conditional Approval KEVIN BERBERYAN
BUILDING-Rough-Frame 11/12/2025 Approved MATTHEW NELSON
Insulation 11/12/2025 Approved MATTHEW NELSON
Wood Frame 11/12/2025 Approved MATTHEW NELSON
Drywall Nailing 11/26/2025 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 11/26/2025 Partial Approval NICHOLAS TROWBRIDGE
Shower Pan 12/1/2025 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 12/4/2025 Approved NICHOLAS TROWBRIDGE
SGSOV-Seismic Gas S/O Valve 12/30/2025 SGSOV Not Ready NICHOLAS TROWBRIDGE
Final 1/6/2026 Corrections Issued NICHOLAS TROWBRIDGE
SGSOV-Seismic Gas S/O Valve 1/6/2026 SGSOV Approved NICHOLAS TROWBRIDGE
Smoke Detectors 1/6/2026 Approved NICHOLAS TROWBRIDGE
Final 1/29/2026 Corrections Issued NICHOLAS TROWBRIDGE
ELECTRICAL-Final 2/2/2026 Not Ready for Inspection NICHOLAS TROWBRIDGE
Service/Power Release 2/2/2026 Not Ready for Inspection NICHOLAS TROWBRIDGE
ELECTRICAL-Final 2/4/2026 Approved NICHOLAS TROWBRIDGE
Final 2/4/2026 OK to Issue CofO NICHOLAS TROWBRIDGE