10825 N MCVINE AVE 91040
Certificate Information: 10825 N MCVINE AVE 91040
- Application / Permit
- 25016-20000-21572
- Plan Check / Job No.
- B25VN19872
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 66323(a)(1)
- Permit Issued
- Issued on 8/13/2025
- Issuing Office
- Current Status
- CofO Issued on 3/12/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/17/2025 | MADISON ODELL |
| Corrections Issued | 7/17/2025 | MADISON ODELL |
| Plan Check Approved | 8/12/2025 | GURUNATH NESARAJAH |
| Issued | 8/13/2025 | APPLICANT |
| CofO in Progress | 2/5/2026 | NICHOLAS TROWBRIDGE |
| Permit Finaled | 3/12/2026 | RUBEN SALAS |
| CofO Issued | 3/12/2026 | RUBEN SALAS |
| Permit Finaled | 3/12/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/23/2025 | ALEXANDER HELFER |
| Address approval | Cleared | 7/25/2025 | TAL SHEMEN |
| Sewer availability | Cleared | 7/25/2025 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 8/3/2025 | TAL SHEMEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: C93079 | 15445 VENTURA BLVD #63 SHERMAN OAKS, CA 91403 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/25/2025 | Partial Inspection | WILLIAM WREN |
| Deputy Drilled-In Anchors | 10/1/2025 | Conditional Approval | WILLIAM WREN |
| Underground Mechanical | 10/2/2025 | Partial Approval | WILLIAM WREN |
| Footing/Foundation/Slab | 10/15/2025 | Approved | WILLIAM WREN |
| HVAC-Rough | 10/15/2025 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 10/15/2025 | Approved | WILLIAM WREN |
| Sewer | 10/15/2025 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 10/24/2025 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 10/24/2025 | Partial Inspection | MISAEL ESPARZA |
| Insulation | 11/5/2025 | Partial Approval | KEVIN BERBERYAN |
| Wood Frame | 11/5/2025 | Conditional Approval | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 11/12/2025 | Approved | MATTHEW NELSON |
| Insulation | 11/12/2025 | Approved | MATTHEW NELSON |
| Wood Frame | 11/12/2025 | Approved | MATTHEW NELSON |
| Drywall Nailing | 11/26/2025 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 11/26/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Shower Pan | 12/1/2025 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 12/4/2025 | Approved | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 12/30/2025 | SGSOV Not Ready | NICHOLAS TROWBRIDGE |
| Final | 1/6/2026 | Corrections Issued | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 1/6/2026 | SGSOV Approved | NICHOLAS TROWBRIDGE |
| Smoke Detectors | 1/6/2026 | Approved | NICHOLAS TROWBRIDGE |
| Final | 1/29/2026 | Corrections Issued | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Final | 2/2/2026 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Service/Power Release | 2/2/2026 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Final | 2/4/2026 | Approved | NICHOLAS TROWBRIDGE |
| Final | 2/4/2026 | OK to Issue CofO | NICHOLAS TROWBRIDGE |