22329 W GIFFORD ST 91303

Certificate Information: 22329 W GIFFORD ST 91303

Application / Permit
25016-20000-21558
Plan Check / Job No.
B25VN19863
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GC 66323(a)(1).
Permit Issued
Issued on 8/8/2025
Issuing Office
Current Status
CofO Issued on 12/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/13/2025 APPLICANT
Assigned to Plan Check Engineer 7/16/2025 ROSENDO MEDINA
Corrections Issued 7/17/2025 ROSENDO MEDINA
Plan Check Approved 8/4/2025 ROSENDO MEDINA
Issued 8/8/2025 APPLICANT
CofO in Progress 12/9/2025 JEFFREY HARTLINE
Permit Finaled 12/18/2025 JOHN JANSON
CofO Issued 12/18/2025 JOHN JANSON
Permit Finaled 12/18/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/24/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 7/24/2025 SAFA JAVANMARDI
Permit Cleared 7/24/2025 SAFA JAVANMARDI
Sewer availability Cleared 7/24/2025 SAFA JAVANMARDI
Construction near power lines Cleared 7/30/2025 GEVORK KARAPETYAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/11/2025 Conditional Approval JEFFREY HARTLINE
Footing/Foundation/Slab 8/12/2025 Approved JEFFREY HARTLINE
Pre-Inspection 8/12/2025 Partial Approval JEFFREY HARTLINE
Sewer 8/12/2025 Approved JEFFREY HARTLINE
Underground Mechanical 8/12/2025 Approved JEFFREY HARTLINE
Wood Frame 8/12/2025 Not Ready for Inspection JEFFREY HARTLINE
BUILDING-Rough-Frame 8/20/2025 Not Ready for Inspection JEFFREY HARTLINE
ELECTRICAL-Rough 8/20/2025 Approved JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 8/20/2025 Partial Approval JEFFREY HARTLINE
PLUMBING-Rough 8/20/2025 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 8/28/2025 Approved JEFFREY HARTLINE
Green Building Rough 8/28/2025 Approved JEFFREY HARTLINE
HVAC-Rough 8/28/2025 Approved JEFFREY HARTLINE
Insulation 9/4/2025 Approved JEFFREY HARTLINE
Shower Pan 9/4/2025 Approved JEFFREY HARTLINE
Drywall Nailing 9/9/2025 Approved GEVORK IPCHYAN
Interior/Exterior Lathing 9/9/2025 Partial Approval GEVORK IPCHYAN
Gas Test 10/16/2025 Approved HENRY KIM
ELECTRICAL-Final 10/29/2025 Not Ready for Inspection JEFFREY HARTLINE
Final 10/29/2025 Corrections Issued JEFFREY HARTLINE
Green Building Final 10/29/2025 Not Ready for Inspection JEFFREY HARTLINE
HVAC-Final 10/29/2025 Approved JEFFREY HARTLINE
PLUMBING-Final 10/29/2025 Approved JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 10/29/2025 SGSOV Approved JEFFREY HARTLINE
Smoke Detectors 10/29/2025 Not Ready for Inspection JEFFREY HARTLINE
Final 11/14/2025 Not Ready for Inspection JEFFREY HARTLINE
Green Building Final 11/14/2025 Not Ready for Inspection JEFFREY HARTLINE
Smoke Detectors 11/14/2025 Approved JEFFREY HARTLINE
ELECTRICAL-Final 12/8/2025 Approved JEFFREY HARTLINE
Final 12/8/2025 OK to Issue CofO JEFFREY HARTLINE
Green Building Final 12/8/2025 Approved JEFFREY HARTLINE
Service/Power Release 12/8/2025 Approved JEFFREY HARTLINE