6636-6638 N WHITAKER AVE 91406

Certificate Information: 6636-6638 N WHITAKER AVE 91406

Application / Permit
25016-20000-21506
Plan Check / Job No.
B25VN19803
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER GC 66323(a)(1).
Permit Issued
Issued on 9/23/2025
Issuing Office
Current Status
CofO Issued on 7/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/11/2025 APPLICANT
Assigned to Plan Check Engineer 7/17/2025 JESSE ARELLANO
Corrections Issued 7/19/2025 JESSE ARELLANO
Building Plans Picked Up 8/7/2025 APPLICANT
Plan Check Approved 8/26/2025 ISIS ARGUETA
Issued 9/23/2025 APPLICANT
CofO in Progress 7/2/2026 MICHAEL CORTEZ
CofO Issued 7/9/2026 RUBEN SALAS
Permit Finaled 7/9/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/30/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 7/30/2025 BIAINA HARITUNIAN
Sewer availability Cleared 7/30/2025 BIAINA HARITUNIAN

Contact Information

Contractor La Family Builders Inc ; Lic. No.: 1120579-B 6355 TOPANGA CANYON BLVD UNIT 331      WOODLAND HIILS, CA 91367
Engineer Shmeit,, Ayman Ivan; Lic. No.: C93325 16905 ARMDORE AVE      BELLFLOWER, CA 90706

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 9/26/2025 Approved WAYNE REGESTER
Underground Mechanical 9/26/2025 Approved WAYNE REGESTER
Deputy Drilled-In Anchors 10/10/2025 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 10/10/2025 Approved GAREN HAYRAPETYAN
ELECTRICAL-Rough 2/20/2026 Corrections Issued GAREN HAYRAPETYAN
HVAC-Rough 2/20/2026 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 2/20/2026 Corrections Issued GAREN HAYRAPETYAN
BUILDING-Rough-Frame 2/24/2026 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Rough 2/24/2026 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 2/24/2026 Corrections Issued KIRK SANDERS
HVAC-Rough 2/24/2026 Approved KIRK SANDERS
PLUMBING-Rough 2/24/2026 Approved KIRK SANDERS
BUILDING-Rough-Frame 3/11/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 3/11/2026 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 3/11/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 3/16/2026 Conditional Approval KIRK SANDERS
Green Building Rough 3/16/2026 Not Ready for Inspection KIRK SANDERS
Interior/Exterior Lathing 3/16/2026 Partial Approval KIRK SANDERS
Wood Frame 3/16/2026 Conditional Approval KIRK SANDERS
BUILDING-Rough-Frame 3/24/2026 Approved KIRK SANDERS
Green Building Rough 3/24/2026 Approved KIRK SANDERS
Insulation 3/24/2026 Approved KIRK SANDERS
Shower Pan 3/24/2026 Approved KIRK SANDERS
Drywall Nailing 3/27/2026 Approved JOSE AVILA
Interior/Exterior Lathing 3/27/2026 Approved JOSE AVILA
Shower Pan 3/27/2026 Approved JOSE AVILA
Interior/Exterior Lathing 4/9/2026 Partial Approval DAVID MATSON
Final 6/8/2026 Corrections Issued MICHAEL CORTEZ
Green Building Final 6/8/2026 Approved MICHAEL CORTEZ
SGSOV-Seismic Gas S/O Valve 6/8/2026 SGSOV Approved MICHAEL CORTEZ
Smoke Detectors 6/8/2026 Approved MICHAEL CORTEZ
ELECTRICAL-Final 6/10/2026 Approved MICHAEL CORTEZ
Final 6/10/2026 Corrections Issued MICHAEL CORTEZ
HVAC-Final 6/10/2026 Approved MICHAEL CORTEZ
PLUMBING-Final 6/10/2026 Approved MICHAEL CORTEZ
Final 7/2/2026 OK to Issue CofO MICHAEL CORTEZ