19012 W BESSEMER ST 91335

Certificate Information: 19012 W BESSEMER ST 91335

Application / Permit
25016-20000-21186
Plan Check / Job No.
B25VN19436
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: convert (E)18'x20' detached Garage to ADU per WFPP (ADU Ordinance Type, New Construction ,or Conversion of Existing ADU Per LAMC 12.22 A.33(b)(1) )
Permit Issued
Issued on 9/30/2025
Issuing Office
Current Status
CofO in Progress on 6/2/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/8/2025 APPLICANT
Assigned to Plan Check Engineer 7/14/2025 AUNG SOE
Corrections Issued 7/16/2025 AUNG SOE
Applicant returned to address corrections 9/29/2025 AUNG SOE
Plan Check Approved 9/29/2025 AUNG SOE
Issued 9/30/2025 APPLICANT
CofO in Progress 6/2/2026 JON MCHUGH

Permit Application Clearance Information

ZI Cleared 8/5/2025 DAVID URITA
Address approval Cleared 8/7/2025 BIAINA HARITUNIAN
Sewer availability Cleared 8/7/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 8/8/2025 BIAINA HARITUNIAN
Construction near power lines Cleared 9/2/2025 GEVORK KARAPETYAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/15/2025 Not Ready for Inspection JON MCHUGH
PLUMBING-Rough 10/15/2025 Not Ready for Inspection JON MCHUGH
Sewer 10/15/2025 Corrections Issued JON MCHUGH
PLUMBING-Rough 10/20/2025 Partial Approval DAVID SCANTLIN
Sewer 10/20/2025 Approved DAVID SCANTLIN
Underground Mechanical 10/22/2025 Not Ready for Inspection JON MCHUGH
Underground Mechanical 10/24/2025 Partial Approval JON MCHUGH
Footing/Foundation/Slab 11/19/2025 Approved JON MCHUGH
Green Building Rough 12/16/2025 Not Ready for Inspection JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 12/18/2025 Partial Approval JON MCHUGH
ELECTRICAL-Rough 1/5/2026 Corrections Issued JON MCHUGH
PLUMBING-Rough 1/5/2026 Corrections Issued JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 1/14/2026 Approved JON MCHUGH
ELECTRICAL-Rough 1/21/2026 Not Ready for Inspection JON MCHUGH
HVAC-Rough 1/21/2026 Not Ready for Inspection JON MCHUGH
Interior/Exterior Lathing 1/21/2026 Corrections Issued JON MCHUGH
PLUMBING-Rough 1/21/2026 Not Ready for Inspection JON MCHUGH
ELECTRICAL-Final 2/2/2026 Corrections Issued JON MCHUGH
ELECTRICAL-Rough 2/2/2026 Approved JON MCHUGH
HVAC-Rough 2/2/2026 Approved JON MCHUGH
Interior/Exterior Lathing 2/2/2026 Partial Approval JON MCHUGH
Drywall Nailing 2/20/2026 Not Ready for Inspection JON MCHUGH
Insulation 2/20/2026 Approved JON MCHUGH
Interior/Exterior Lathing 2/20/2026 Approved JON MCHUGH
Shower Pan 2/20/2026 Not Ready for Inspection JON MCHUGH
Drywall Nailing 2/24/2026 Approved JUAN ALVARADO
BUILDING-Rough-Frame 4/14/2026 Not Ready for Inspection MORRIS JACKSON
Green Building Final 4/14/2026 No Access for Inspection MORRIS JACKSON
Green Building Rough 4/14/2026 Not Ready for Inspection MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 4/14/2026 SGSOV Not Ready MORRIS JACKSON
Smoke Detectors 4/14/2026 Not Ready for Inspection MORRIS JACKSON
BUILDING-Rough-Frame 4/29/2026 Approved JON MCHUGH
Final 4/29/2026 Corrections Issued JON MCHUGH
Green Building Rough 4/29/2026 Approved JON MCHUGH
Final 5/13/2026 Partial Approval JON MCHUGH
Green Building Final 5/13/2026 Approved JON MCHUGH
SGSOV-Seismic Gas S/O Valve 5/13/2026 SGSOV Approved JON MCHUGH
Smoke Detectors 5/13/2026 Approved JON MCHUGH
Final 6/2/2026 OK to Issue CofO JON MCHUGH