14077-14079 W RYAN ST 91342
Certificate Information: 14077-14079 W RYAN ST 91342
- Application / Permit
- 25016-20000-21121
- Plan Check / Job No.
- B25VN19334
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN CONVERT (E) ATTACHED 2-CAR GARAGE TO JUNIOR ACCESSORY DWELLING UNIT (JADU) WORK PER WFPP
- Permit Issued
- Issued on 9/16/2025
- Issuing Office
- Current Status
- Issued on 9/16/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/8/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2025 | CRYSTEL MAALOUF |
| Corrections Issued | 7/15/2025 | CRYSTEL MAALOUF |
| Plan Check Approved | 9/10/2025 | NEHEMIAS RAMOS |
| Issued | 9/16/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/24/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 7/24/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 7/28/2025 | SAFA JAVANMARDI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/15/2025 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 11/3/2025 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 11/3/2025 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 11/3/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| HVAC-Rough | 11/3/2025 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 11/3/2025 | Approved | KEVIN BERBERYAN |
| Rough-Elec/Plmb/HVAC | 11/3/2025 | Approved | KEVIN BERBERYAN |
| Shower Pan | 11/3/2025 | Approved | KEVIN BERBERYAN |
| Insulation | 11/5/2025 | Approved | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2025 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 11/6/2025 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 11/7/2025 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 11/10/2025 | Approved | CHRISTOPHER MORFIN |
| BUILDING-Rough-Frame | 12/2/2025 | Approved | KEVIN BERBERYAN |
| Final | 12/2/2025 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 12/2/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Green Building Rough | 12/2/2025 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 12/2/2025 | SGSOV Approved | KEVIN BERBERYAN |
| Smoke Detectors | 12/2/2025 | Approved | KEVIN BERBERYAN |